S.D. Highway 46 through Wagner
Project Summary:
This project will consist of grading, surfacing, curb & gutter, sidewalk, lighting, signals, sanitary sewer, and water main. Crews will be regrading S.D. Highway 46 through Wagner with a three-lane section east of Washington Avenue and a five-lane section west of Washington Avenue. New lighting and sidewalks will be added through town along with crosswalks with flashing beacons that will improve safety for pedestrians. During the project, the City of Wagner is also installing new sanitary sewer and water main to upgrade their existing systems to ensure future reliability.
Grading
Resurfacing
Lighting and Sidewalks
Sign Up for Text Notifications:
For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time.
Text WAGNER46 to 605-566-4041
Project Updates:
May 20, 2026:
Anticipated work from May 15, 2026, to June 15, 2026: The contractor will continue infrastructure improvements, including pipe installation, grading, and paving. Work will progress from east to west on the south side of Highway 46.
Storm sewer, sanitary sewer, and water service installation will continue to Walnut Avenue. Paving operations will extend to Buche Foods, with sidewalk installation to follow roadway improvements.
Motorists are reminded to use caution in the work zone. A 15 mph speed limit is in effect in the school zone when children are present. Flashing beacons have been temporarily removed and are scheduled for replacement.
Completed work from April 15, 2026, to May 15, 2026: The contractor made significant progress on the south side of South Dakota Highway 46 from Grant Avenue to the west city limits. Work included installation of temporary sidewalk, refreshed pavement striping, and implementation of traffic control. Asphalt, concrete, and base course were removed and processed for reuse on the project.
Storm sewer, sanitary sewer, and water services were installed along West Avenue. Paving operations progressed to Main Avenue.
Project Photos:
Schedule:
Spring 2025 - Nov. 2025: From East Ave SE to the east end of Wagner City Limits
Spring 2026 - Nov. 2026: Western half of S.D. Highway 46 from Grant Ave SE to the west end of Wagner City Limits
Spring/Summer 2027: Completing the durable pavement markings on S.D. Highway 46 throughout this project
Location:
S.D. Highway 46 Through Wagner
Benefits:
Grading
Resurfacing
Lighting and Sidewalks
Estimated Cost:
$21 Million
Contractor:
A & R Construction of Plainview, NE
PCN: 05JN
© 2026 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
Region & Area Offices
Travelers
© 2026 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic