Euclid Ave in Pierre Construction Map


Project Updates:

July 22, 2026:

On Friday, July 24, 2026, Euclid Avenue and Elizabeth Street will reopen to through traffic in Pierre. When north of Wynoka Avenue, motorists on Euclid Avenue will remain in a two-way configuration with lane shifts until all remaining work is completed. A 10-foot width restriction will be in effect. The intersection of Euclid Avenue and Elizabeth Street will be controlled by a four-way stop. Traffic signals at the Elizabeth Street intersection will be activated when all adjacent work has been completed and traffic lane lines are installed.

The east leg of the 4th Street intersection will be reopened in the coming weeks. At that time, the west leg will be closed to accommodate construction of the southbound lanes and west 4th Street.

Commuters should proceed through the work zone at slow speeds and be attentive for construction workers and equipment. Minimal delay is anticipated.

--

July 21, 2026:

Anticipated Work in August 2026:

On Euclid Avenue (from Broadway Avenue thru Elizabeth Street):

Contractor will be installing sidewalk and approaches to private accesses, alleys, and businesses.

Boulevard grading, along with topsoil placement will be underway.

Traffic will be in a two-way configuration as the contractor utilizes the outside through lanes to conduct work behind the curb and gutter.

On Euclid Avenue (from Elizabeth Street to 4th Street):

Traffic is in a two-way configuration in the southbound lanes while curb and gutter and asphalt surfacing is placed for the northbound lanes. Luminaire poles will be installed. Once the prior work is complete, traffic will be switched to a two-way configuration in the new northbound lanes as surfacing removal begins in the southbound lanes.

Basecourse, curb and gutter, fillets, asphalt surfacing and signal poles will be installed on the east leg of Fourth street. The east leg of Fourth Street should re-open by mid-August. The west leg will then close.

On Euclid Avenue (from 4th Street north to the divided 4-lane north of 8th Street):

Traffic is currently in a two-way configuration in the southbound lanes.

Two lifts of asphalt will be placed on the basecourse for the new northbound lanes. Traffic will be switched to a two-way configuration utilizing the northbound lanes as the contractor begins surfacing removal of the southbound lanes.

Elizabeth Street (From Grand Avenue to Euclid Avenue):

Elizabeth Street will be opened to traffic in a two-way configuration with the contractor working adjacent to the curb to complete remaining work.

Concrete will be placed for sidewalk, private, and alley access. Grading behind the curb will be underway.

Completed Work in July 2026:

On July 24, 2026, Euclid Avenue was again opened for through traffic. Commuters can again drive through the entire project.

On Euclid Avenue (from Broadway Avenue thru Elizabeth Street):

All curb and gutter along with side street fillets have been placed.

All mainline and side street asphalt has been placed.

Luminaire poles are installed and active.

Permanent pavement markings were installed

On Euclid Avenue (from Elizabeth Street to 4th Street):

Traffic remained in a two-way configuration in the southbound lanes.

City water has been relocated allowing for all pipe under the northbound lanes to be placed.

Basecourse placement is near complete.

The storm sewer tie in at 4th Street is complete.

The east leg of the 4th Street intersection remains closed for storm sewer tie in, basecourse placement, fillet placement, traffic signals, and final surfacing.

On Euclid Avenue (from 4th Street north to the divided four-lane north of Eighth Street):

Traffic remained in a two-way configuration in the southbound lanes.

Undercut and basecourse placement is completed.

Elizabeth Street (From Grand Avenue to Euclid Avenue):

Curb and gutter along with all three lifts of asphalt has been placed.

Luminaires were installed.

Elizabeth Street was re-opened to traffic on July 24, 2026.

Click to view updated maps of project

2026 Construction Schedule: 

Euclid Ave 2026 construction schedule and map

 

Project Summary:

Urban reconstruction, asphalt and concrete surfacing, storm sewer, lighting, signals, sanitary sewer and water main replacement.

  • U.S. Highway 14/83 (Euclid Avenue) – from Sioux Avenue intersection to the divided highway west of S.D. Highway 1804 in Pierre.​

  • Elizabeth Street (between Highway 14 and Grand Avenue).​

  • Wynoka Street drainage outfall.

Sign Up for Text Notifications:

For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time. 

Text EUCLID to 605-566-4041

 

Detour Map:

    Euclid Ave detour map


Project Photos:

Schedule:

  • Year One: Spring 2025 - Fall 2025

  • Year Two: Spring 2026 - Nov. 2026

Location:

  • S.D. Highway 1889 - Euclid Ave

Benefits:

  • Urban Grading

  • Curb and Gutter

  • Traffic Signals

Estimated Cost:

  • 26.4 Million

Contractor:

  • Morris Inc.

PCN: 026Z 