S.D. Highway 46 Through Wagner

wagner-46.png

Project Summary:

This project will consist of grading, surfacing, curb & gutter, sidewalk, lighting, signals, sanitary sewer, and water main. Crews will be regrading S.D. Highway 46 through Wagner with a three-lane section east of Washington Avenue and a five-lane section west of Washington Avenue. New lighting and sidewalks will be added through town along with crosswalks with flashing beacons that will improve safety for pedestrians. During the project, the City of Wagner is also installing new sanitary sewer and water main to upgrade their existing systems to ensure future reliability.

  • Grading
  • Resurfacing
  • Lighting and Sidewalks

Sign Up for Text Notifications:

For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time. 

Text WAGNER46 to 605-566-4041

Project Timeline:

Spring 2025 - Nov. 2025: From East Ave SE to the east end of Wagner City Limits

Spring 2026 - Nov. 2026: Western half of S.D. Highway 46 from Grant Ave SE to the west end of Wagner City Limits

Spring/Summer 2027: Completing the durable pavement markings on S.D. Highway 46 throughout this project

Project Updates:

June 20, 2025:

May 15, 2025 – June 15, 2025, Completed Work: The contractor has made significant progress on the south side of Highway 46, from the east end of the city limits heading west. Key accomplishments include: 

  • Installation of a water wall traffic barrier to enhance worker and public safety. 
  • Removal of existing asphalt, concrete, and base course materials. 
  • Installation of 1,500 feet of storm sewer concrete pipe with inlet collection boxes. 
  • Preparation of a stable road base by removing unsuitable material and compacting the subgrade. 
  • Initiation of concrete paving, with the first 1,000 feet of the eastbound driving lane. 

 

Anticipated work in June 15, 2025 – July 15, 2025:  In the coming month, the contractor will continue installing infrastructure improvements by staging out additional pipe, grading, and paving operations. Work will progress from east to west on the south side of Highway 46 including: 

  • Storm sewer, sanitary sewer, and water service installation through Front Avenue. 
  • Continued paving operations extending to the National Guard Armory. 
  • Sidewalk installation to follow roadway improvements. 
  • We appreciate the public’s patience as we work to improve the safety and quality of this key transportation corridor. 

Project Photos:



Project Contract Amount:

$21 Million

Project Contacts

SDDOT:
Travis Holthaus
605-995-3341


Contractor:
A & R Construction of Plainview, NE

STATEWIDE CONSTRUCTION PROJECTS PAGE

 

 

PCN: 05JN