S.D. Highway 44 Platte-Winner Bridge

PlatteWinnerBridgeProjectMap.png

image (4).png
 

Project Updates:

Nov. 19, 2026:

Anticipated work in Dec. 2026: Construction of the barge docks will continue through the winter months. The west-side dock is approximately 25% complete and is scheduled for completion in mid-March 2027. Construction of the east-side dock is anticipated to begin in mid-December and is scheduled for completion in mid-April 2027.

Additional work activities will include continued clearing operations and site preparation to support ongoing construction.

Completed work in Nov. 2026: Crews completed tree clearing operations along the east riverbank in preparation for upcoming construction activities.

--

Oct. 19, 2026:

Anticipated Work in Oct. 2026: Project started on Oct. 3, 2026. For the remainder of October, crews will set up traffic control, mobilize equipment, and begin constructing the docks that will be used for barges.

Platte Winner Bridge Project: 

It is anticipated that construction will begin in early 2027 with completion in 2031, to include the removal of the existing bridge. The new bridge will include the addition of shoulders to provide a total width of 36 ft. compared to the current 28 ft. width. The existing bridge will carry traffic during construction and will be removed from the river after completion of the new bridge and highway.

Construction Impacts:
The existing bridge will remain open throughout construction and will not be demolished until the new bridge is complete. While the bridge will remain open, motorists should expect occasional, temporary impacts to travel. At times, construction activities may require lane closures with alternating one-way traffic or brief stops to allow construction equipment to move safely through the work zone. These temporary disruptions are anticipated to be minimal to maintain safe and efficient traffic flow during construction.

Project Communication:
In advance of construction, we have already started a featured project page https://dot.sd.gov/plattewinnerbridge/ to help provide information and answer questions for the public about this monumental project. For updates on major traffic changes, a free text-in service is also available. To subscribe, simply text PLATTEWINNERBRIDGE to 605-566-4041.

Corridor Study:
The corridor study for replacement of the Highway 44 (Platte-Winner) Bridge may be found at https://sd44bridge.com/.

Project Photos:

Schedule:

  • 2027-2031

Location:

  • S.D. Highway 44 - Platte/Winner Bridge over Missouri River

Benefits:

  • Improved Safety and Reliability

  • Enhanced Traffic Flow

Estimated Cost:

  • $290 Million

Contractor:

  • Ames Construction of Burnsville, MN

PCN: 05XO