S.D. Highway 11 North of Brandon
Project Summary:
The project will reconstruct approximately one and one-half miles of roadway, including replacing two bridges over West Pipestone Creek and Split Rock Creek.
The roadway will be raised approximately 10 to 12 feet through the low-lying valley to reduce flooding impacts and improve long-term reliability. Once complete, the new asphalt surface will provide a smoother ride for motorists and help reduce future maintenance needs.
Project FAQ's:
Yes. This one and one- half mile stretch of Highway 11 is being raised up to 11 feet. By raising the road, there is a reduction in the risk of flooding and an increase in sight distance, removing “valleys” on this roadway.
Highway 11 is anticipated to close on Monday, June 1, 2026, until Spring 2027. Contractors will use this time to replace two structures.
Yes. The bridges over West Pipestone Creek and Split Rock Creek are being replaced. Both these structures were built in 1952 and have reached the end of their useful life.
Travelers can expect five to ten minute delays, with both detour routes on paved county highways.
Detour Maps:
Project Updates:
April 17, 2026:
Anticipated Work - April 2026:
Contractor crews will continue grading outside the shoulders along S.D. Highway 11, County Highway 130 and 257th Street. Highway 11 and Highway 130 will remain open until after Monday, June 1, 2026, though drivers may see closures at the intersections of 257th Street and Palisade Street before that date.
Multiple utility companies are also working on relocations along Highway 11 and Highway 130.
In March 2026, the contractor began grading outside the shoulders and started hauling borrow material from pits near Knife River. Metal pipe culverts were installed in field approaches and driveways. Utility companies have been relocating gas, fiber and electrical lines.
Project Photos:
PCN: 05V6
Schedule:
April 2026 - Summer 2027
Location:
S.D. Highway 11 from 257th Street to 258th Street
Three miles north of Brandon
Travel Impacts:
S.D. Highway 11 will be closed from June 1, 2026, through the spring of 2027. Main detour in effect from September 2026 to Spring 2027.
Intersection of S.D. Highway 11 and County Highway 130 (258th St.) will be closed from June 1, 2026, to September 2026. The contractor has 70 days for this closure. Please use the alternative detour route.
Benefits:
Structure replacement
Reduction of flood impacts
Resurfacing
Reduce future maintenance needs
Estimated Cost:
$14.9 Million
Contractor:
Runge Enterprises, Inc.
PCN: 05V6
© 2026 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
Region & Area Offices
Travelers
© 2026 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic


