Interstate 90 Bridges in Mitchell

Project Summary:

The project includes replacing bridge approach slabs and joints to provide a smoother transition on and off the structure. Berm repairs and improvements to the approach pavement will also be completed to enhance ride quality and extend the life of the roadway.

A polymer chip seal will be applied to help protect the surface from moisture and wear. Guardrail upgrades will improve roadside safety, and an acceleration lane will be constructed to allow drivers to safely merge into traffic.

Project Updates:

June 29, 2026:

Anticipated Work in July 2026:

Bridge repair work and placement of the polymer epoxy chip seal wearing surface on the eastbound and westbound bridge decks will be completed.

Concrete will be poured for the westbound deceleration lane.

Construction of the eastbound acceleration lane embankment will continue.

Completed Work in June 2026:

Bridge repair work continued in the driving lanes. The approach slabs were removed, and repair work is nearing completion.

Grading operations also began for the eastbound acceleration lane.

Exit 332 Closure - Detour Route:

Overwidth Detour Map:



Project Photos:

 

Schedule:

  • April 2026 - Oct. 30, 2026

Location:

  • Interstate 90 eastbound and westbound - 0.2 miles east of S.D. Highway 37 south interchange over the railroad; I-90 from east of exit 332 (S.D. Highway 37 south) eastbound on-ramp to 0.3 miles east

Benefits:

  • Approach Slabs

  • Joints

  • Berm Repair

  • Approach Pavement

  • Polymer Chip Seal

  • Guardrail

  • Acceleration Lane

Estimated Cost:

  • $2.7 Million

Contractor:

  • T & R Construction of Sioux Falls, SD

PCN: 091U