S.D. Highway 28 in Toronto

S.D. Highway 28 in Toronto Project Location Map

Project Summary:

The project will fully reconstruct the roadway through Toronto, including utility upgrades, new curb and gutter, and new lighting.

Crews will also place a new asphalt concrete surface and add sidewalks throughout the project limits to improve safety and accessibility for all users.

The road will stay open during construction, with traffic alternating through a single lane.

Sign Up for Text Notifications:

For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time. 

Text TORONTO28 to 605-566-4041

Project Updates:

June 29, 2026:

Anticipated Work in July 2026:

The contractor will continue grading operations and undercut excavation on Phase 1. The contractor also plans to complete salvage gravel placement and make significant progress on curb and gutter and sidewalk construction during July.

Completed Work in June 2026:

The contractor completed storm sewer installation and drop inlet construction on Phase 1. Grading operations also began from Dakota Street to the east city limits as part of Phase 1.

--

May 20, 2026:

Anticipated work in June 2026: The contractor is expected to complete storm sewer installation for phase 1 (north half of the roadway) by early June and will continue drop inlet placement. Grading and gravel placement for phase 1 will begin. Curb and gutter and sidewalk placement are anticipated in late June.

Completed work in May 2026: Storm sewer installation from Pheasant Street to Frontier Street complete, with three of five blocks finished. Drop inlet placement from Dakota Street to Frontier Street is expected to be complete, with two of five blocks finished.

Project Photos:

Schedule:

  • April 2026 - Nov. 2026

Location:

  • S.D. Highway 28 - Toronto

Benefits:

  • Full urban reconstruction

  • Utility upgrades

  • Lighting

  • Resurfacing

  • Sidewalk

Estimated Cost:

  • $2,193,245.87

Contractor:

  • Bowes Construction, Inc.

PCN: 06R7

STATEWIDE CONSTRUCTION PROJECTS PAGE