S.D. Highway 28 in Toronto
Project Summary:
The project will fully reconstruct the roadway through Toronto, including utility upgrades, new curb and gutter, and new lighting.
Crews will also place a new asphalt concrete surface and add sidewalks throughout the project limits to improve safety and accessibility for all users.
The road will stay open during construction, with traffic alternating through a single lane.
Sign Up for Text Notifications:
For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time.
Text TORONTO28 to 605-566-4041
Project Updates:
May 20, 2026:
Anticipated work in June 2026: The contractor is expected to complete storm sewer installation for phase 1 (north half of the roadway) by early June and will continue drop inlet placement. Grading and gravel placement for phase 1 will begin. Curb and gutter and sidewalk placement are anticipated in late June.
Completed work in May 2026: Storm sewer installation from Pheasant Street to Frontier Street complete, with three of five blocks finished. Drop inlet placement from Dakota Street to Frontier Street is expected to be complete, with two of five blocks finished.
Project Photos:
Schedule:
April 2026 - Nov. 2026
Location:
S.D. Highway 28 - Toronto
Benefits:
Full urban reconstruction
Utility upgrades
Lighting
Resurfacing
Sidewalk
Estimated Cost:
$2,193,245.87
Contractor:
Bowes Construction, Inc.
PCN: 06R7
STATEWIDE CONSTRUCTION PROJECTS PAGE
© 2026 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
Region & Area Offices
Travelers
© 2026 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
