Interstate 29 Bridge Rehabilitation Sioux Falls - Over Skunk Creek

sfareaskunkcreek.png

Project Summary:

Interstate 29 north and south - approximately ½ mile north of 26th Street over Skunk Creek, over 12th Street (exit 79), approximately ½ mile north of 12th Street over Ellis & Eastern Railroad. 

  • Bridge Deck Overlay
  • Approach Slabs
  • Guardrail

Sign Up for Text Notifications:

For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time. 

Text I29Bridges to 605-566-4041

Project Timeline:

Spring 2025 - Fall 2025

Project Updates:

Sept. 3, 2025:

On Monday, Sept. 8, 2025, traffic control will be switched to allow motorists to utilize the newly constructed eastern most two lanes on the southbound Interstate 29 structures over 12th Street and the Ellis & Eastern Railroad.
 
This configuration is anticipated to be in place until Friday, Oct.10, 2025, to allow for work on the western most two lanes of southbound I-29 structures over 12th Street and the Ellis & Eastern Railroad. Upon completion, traffic control will be removed and traffic will be restored to their respective lanes.

---

Sept. 17, 2025: 

Sept. 15 – Oct. 15, 2025, Completed Work:

I-29 northbound bridge over Skunk Creek

  • Phase 2 (west lanes) pile repair was completed. Work continued on approach slabs and mainline concrete paving.

I-29 southbound bridge over Skunk Creek

  • Phase 2 (west lanes) pile repair was completed. Work continued on approach slabs and mainline concrete paving.

I-29 southbound bridge over Ellis and Eastern Railroad

  • Phase 1 (west lanes) was completed. Traffic was shifted to the east lanes, and removals began for Phase 2 (west lanes).

I-29 southbound bridge over 12th Street

  • Phase 1 (west lanes) was completed. Traffic was shifted to the east lanes, and removals began for Phase 2 (west lanes).

Anticipated Work Oct. 15 – Nov. 15, 2025:

I-29 northbound bridge over Skunk Creek

  • Complete all Phase 2 (west lanes) mainline concrete paving and open to traffic.

I-29 southbound bridge over Skunk Creek

  • Complete all Phase 2 (west lanes) mainline concrete paving and open to traffic.

I-29 southbound bridge over Ellis and Eastern Railroad

  • Complete Phase 2 (west lanes) removals and finish approach and mainline concrete paving.

I-29 southbound bridge over 12th Street

  • Complete Phase 2 (west lanes) removals and finish approach and mainline concrete paving.

Project Photos:



Project Contract Amount:

$7.4 Million

Project Contacts:

SDDOT: 
Brad Tiede
605-367-5680

Contractor:
General Excavating LLC.