Interstate 29 Bridge Rehabilitation Sioux Falls - Over Skunk Creek
Project Summary:
Interstate 29 north and south - approximately ½ mile north of 26th Street over Skunk Creek, over 12th Street (exit 79), approximately ½ mile north of 12th Street over Ellis & Eastern Railroad.
- Bridge Deck Overlay
- Approach Slabs
- Guardrail
Sign Up for Text Notifications:
For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time.
Text I29Bridges to 605-566-4041
Project Timeline:
Spring 2025 - Fall 2025
Project Updates:
Aug. 22, 2025:
July 15–Aug. 15, 2025, Completed work:
I-29 northbound bridge over Skunk Creek
- Phase Two (western half) approach slabs are complete.
- Crews are working on Phase Two mainline paving tie-ins.
I-29 northbound bridge over West 12th Street
- All work is complete.
I-29 northbound bridge over Ellis and Eastern Railroad
- All work is complete.
I-29 southbound bridge over Ellis and Eastern Railroad
- Traffic is in the west two lanes.
- Crews are working in the east two lanes (Phase One), which includes bridge approach slabs, mainline concrete paving, asphalt shoulders, and guardrail.
I-29 southbound bridge over West 12th Street
- Traffic is in the west two lanes.
- Crews are working in the east two lanes (Phase One), which includes bridge approach slabs, mainline concrete paving, asphalt shoulders, and guardrail.
I-29 southbound bridge over Skunk Creek
- Traffic remains in the west two lanes as crews work in the east two lanes (Phase Two).
- Work includes bridge approach slabs, mainline concrete paving, asphalt shoulders, and guardrail.
Anticipated work Aug. 15–Sept. 15, 2025:
I-29 northbound bridge over Skunk Creek
- Crews plan to complete all Phase Two work (western half) and open it to traffic.
I-29 southbound bridge over Ellis and Eastern Railroad
- Crews will complete work in the east two lanes (Phase One), including bridge approach slabs, mainline concrete paving, asphalt shoulders, and guardrail.
I-29 southbound bridge over West 12th Street
- Crews will complete work in the east two lanes (Phase One), including bridge approach slabs, mainline concrete paving, asphalt shoulders, and guardrail.
Project Photos:
Project Contract Amount:
$7.4 Million
Project Contacts:
SDDOT:Brad Tiede
605-367-5680
Contractor:
General Excavating LLC.
STATEWIDE CONSTRUCTION PROJECTS PAGE
PCN: 065E
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
Region & Area Offices
Travelers
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic