Interstate 29 Bridge Rehabilitation Sioux Falls - Over Skunk Creek
Project Summary:
Interstate 29 north and south - approximately ½ mile north of 26th Street over Skunk Creek, over 12th Street (exit 79), approximately ½ mile north of 12th Street over Ellis & Eastern Railroad.
- Bridge Deck Overlay
- Approach Slabs
- Guardrail
Sign Up for Text Notifications:
For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time.
Text I29Bridges to 605-566-4041
Project Timeline:
Spring 2025 - Fall 2025
Project Updates:
Sept. 3, 2025:
On Monday, Sept. 8, 2025, traffic control will be switched to allow motorists to utilize the newly constructed eastern most two lanes on the southbound Interstate 29 structures over 12th Street and the Ellis & Eastern Railroad.
This configuration is anticipated to be in place until Friday, Oct.10, 2025, to allow for work on the western most two lanes of southbound I-29 structures over 12th Street and the Ellis & Eastern Railroad. Upon completion, traffic control will be removed and traffic will be restored to their respective lanes.
---
Sept. 17, 2025:
Sept. 15 – Oct. 15, 2025, Completed Work:
I-29 northbound bridge over Skunk Creek
- Phase 2 (west lanes) pile repair was completed. Work continued on approach slabs and mainline concrete paving.
I-29 southbound bridge over Skunk Creek
- Phase 2 (west lanes) pile repair was completed. Work continued on approach slabs and mainline concrete paving.
I-29 southbound bridge over Ellis and Eastern Railroad
- Phase 1 (west lanes) was completed. Traffic was shifted to the east lanes, and removals began for Phase 2 (west lanes).
I-29 southbound bridge over 12th Street
- Phase 1 (west lanes) was completed. Traffic was shifted to the east lanes, and removals began for Phase 2 (west lanes).
Anticipated Work Oct. 15 – Nov. 15, 2025:
I-29 northbound bridge over Skunk Creek
- Complete all Phase 2 (west lanes) mainline concrete paving and open to traffic.
I-29 southbound bridge over Skunk Creek
- Complete all Phase 2 (west lanes) mainline concrete paving and open to traffic.
I-29 southbound bridge over Ellis and Eastern Railroad
- Complete Phase 2 (west lanes) removals and finish approach and mainline concrete paving.
I-29 southbound bridge over 12th Street
- Complete Phase 2 (west lanes) removals and finish approach and mainline concrete paving.
Project Photos:
Project Contract Amount:
$7.4 Million
Project Contacts:
SDDOT:Brad Tiede
605-367-5680
Contractor:
General Excavating LLC.
STATEWIDE CONSTRUCTION PROJECTS PAGE
PCN: 065E
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
Region & Area Offices
Travelers
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic