U.S. Highway 81 Near Madison

Madison.png

Project Summary:

U.S. Highway 81 - From N of NW 9th Street in Madison to the Lake/Kingsbury/Brookings County Line

  • Asphalt Concrete Resurfacing
  • Full Depth Reclamation
  • Intersection Improvement

Project Timeline:

Fall 2024 - Oct. 2025

Project Updates:

Aug. 27, 2025: 

Work Completed in August 2025:

Remaining areas of old asphalt (8–9 inches deep) were milled and reclaimed. The top 5 inches of asphalt were milled and hauled to the Madison DOT Maintenance Yard, where they were crushed and blended with granular material to produce a base course in a 50/50 asphalt-to-granular mix. The remaining 3–4 inches of asphalt were reclaimed along with 4 inches of below-grade material.

An oil-based prime coat was sprayed over the road surface and covered with sand. This treatment bonds the asphalt to the gravel base.

Anticipated Work in September 2025:

Roadway maintenance, including pothole repairs and mowing of grass/weeds on shoulders.

Asphalt paving is scheduled to begin on Tuesday, Sept. 9, 2025, near 220th Street on the northern end of the project. Weather and contractor schedule dependent. Moving road closures of up to three miles will be in place as paving operations progress southbound.

Project Photos:



Project Contract Amount:

$12.1 Million

Project Contacts:

SDDOT: 
Jason Stefanyuk
605-400-5309


Contractor:
Duininck Inc.of Prinsburg, MN

STATEWIDE CONSTRUCTION PROJECTS PAGE

 

 

PCN: 06PN