U.S. Highway 81 Near Madison
Project Summary:
U.S. Highway 81 - From N of NW 9th Street in Madison to the Lake/Kingsbury/Brookings County Line
- Asphalt Concrete Resurfacing
- Full Depth Reclamation
- Intersection Improvement
Project Timeline:
Fall 2024 - Oct. 2025
Project Updates:
Aug. 27, 2025:
Work Completed in August 2025:
Remaining areas of old asphalt (8–9 inches deep) were milled and reclaimed. The top 5 inches of asphalt were milled and hauled to the Madison DOT Maintenance Yard, where they were crushed and blended with granular material to produce a base course in a 50/50 asphalt-to-granular mix. The remaining 3–4 inches of asphalt were reclaimed along with 4 inches of below-grade material.
An oil-based prime coat was sprayed over the road surface and covered with sand. This treatment bonds the asphalt to the gravel base.
Anticipated Work in September 2025:
Roadway maintenance, including pothole repairs and mowing of grass/weeds on shoulders.
Asphalt paving is scheduled to begin on Tuesday, Sept. 9, 2025, near 220th Street on the northern end of the project. Weather and contractor schedule dependent. Moving road closures of up to three miles will be in place as paving operations progress southbound.
Project Photos:
Project Contract Amount:
$12.1 Million
Project Contacts:
SDDOT:Jason Stefanyuk
605-400-5309
Contractor:
Duininck Inc.of Prinsburg, MN
STATEWIDE CONSTRUCTION PROJECTS PAGE
PCN: 06PN
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
Region & Area Offices
Travelers
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic