U.S. Highway 212 and S.D. Highway 79 Nisland to Newell

Newell.png

Project Summary:

U.S. Highway 212 and S.D. Highway 79 from Nisland to Newell. 

Install new asphalt surfacing on the highway from Nisland to Newell, highway pipe work, reconstruct the southern intersection of U.S. Highway 212 and S.D. Highway 79, and update the sidewalk in Newell for increased accessibility. 

  • Asphalt Resurfacing
  • Intersection Improvement
  • Highway Pipe Work
  • Tree Removals in Newell
  • ADA Sidewalk Improvements 

Sign Up for Text Notifications:

For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time. 

Text Newell212 to 605-566-4041


Project Timeline:

June 2025 - Winter 2025

Project Updates:

Nov. 21, 2025: 

Oct. 15, 2025 – Nov. 15, 2025, Completed Work:
The contractor continued final sidewalk construction along the south side of U.S. Highway 212. Grading and placement of base course material at the southern U.S. Highway 212/S.D. Highway 79 intersection were completed. Asphalt surfacing between Newell and Nisland is finished, along with paving at the southern intersection.

Anticipated Work (Nov. 15, 2025 – Dec. 15, 2025:
Final grading and cleanup throughout Newell will continue as sidewalk work is completed. Miscellaneous cleanup activities will also continue throughout the project limits between Newell and Nisland. All work is anticipated to be completed before winter.

---

Aug. 6, 2025: 

On Monday, Aug. 11, 2025, work will begin on an intersection improvement project that will reconstruct the southern intersection of U.S. Highway 212 and S.D. Highway 79. Motorists will encounter a milled roadway surface and two-way traffic shifted to the southbound lanes on Highway 79 while the new lanes are being constructed.

A temporary all-way stop will be in place at the intersection of Highway 212 and Highway 79. Drivers should use caution and be prepared for construction equipment and workers near the roadway. 

This work is part of a larger construction project to install new asphalt surfacing from Nisland to Newell, reconstruct the southern intersection of Highway 212 and Highway 79, and update the sidewalk through Newell. The overall project completion date is Friday, Nov. 14, 2025. 


Project Photos:


Project Contract Amount:

$8.1 Million

Project Contacts:

SDDOT: 
Jonah Schmagel
605-892-2872

Contractor:
Central Specialties, Inc.
320-762-7289

STATEWIDE CONSTRUCTION PROJECTS PAGE

 

PCN: 04L0, 06CP, 06G1, 06G2