U.S. Highway 18 - Winner to Colome
PROJECT COMPLETE

Project Summary:
Project work consists of various locations of concrete repair, concrete surface grinding of the entire roadway between Winner and Colome, paving of asphalt shoulders along the entire length and bridge approach slab repair. This will create a smoother driving surface and increased safety for the public.
Project Timeline:
April 10, 2023 - November 2023
Project Updates:
June 15, 2024 – July 15, 2024, Completed Work: The contractor has completed PCCP grinding between Gregory and Dallas and has begun grinding on the segment between Dallas and Colome. Sawing and sealing of all concrete joints and random cracks has begun near Burke working towards Gregory.
Anticipated work July 15, 2024 – Aug. 15, 2024: The contractor will continue to perform PCCP grinding between Dallas and Colome and begin on the PCCP grinding through Burke, Gregory and Dallas. They will also begin PCCP grinding near Martin within the next month. The contractor will continue sawing and sealing joints and cracks between Colome and Burke.
Project Photos:
Project Videos:
Project Contract Amount:
4.8 Million
Project Contacts:
Contractor:
Bituminous Paving Inc.
Bill Bajari 320-273-2113
The SDDOT Project Engineer:
Hailey Boese 605-842-0810
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
Region & Area Offices
Travelers
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic