U.S. Highway 14 Reconstruction Iroquois to Lake Preston

Iroquois.png

Project Summary:

U.S. Highway 14 from Iroquois to 2.5 miles west of Lake Preston

  • Concrete Pavement
  • Intersection Modification
  • Pipe Work

Project Timeline:

Summer 2025

Project Updates:

July 22, 2025:

June 15, 2025 – July 15, 2025, Completed Work: The contractor is anticipating mobilizing later in August as their schedule and subcontractors allow.  The separate lighting project within the U.S. Highway 14 and S.D. Highway 25 portions of DeSmet is underway with a number of the existing light poles being removed, underground conduits installed and new lighting foundations being installed along U.S. Highway 14.     

Anticipated work July 15, 2025 – Aug. 15, 2025: Survey and staking work is anticipated and if scheduling of the contractor allows some initial work may begin along U.S. Highway 14, however, this is all tentative and will be announced if this comes to fruition over the following month. The lighting work within DeSmet will continue through the month with minimal disruptions to traffic along S.D. Highway 25 and U.S. Highway 14. 

Project Photos:


Project Contract Amount:

Coming Soon

Project Contacts:

SDDOT: 
Brad Letcher
605-353-7140


Contractor:

STATEWIDE CONSTRUCTION PROJECTS PAGE

 

 

PCN: 079E