U.S. Highway 12 - Between Aberdeen and Mina

4.png
Project Summary:

This project consists of a bridge replacement over Snake Creek. 


Traffic on Highway 12 will be directed to use the on-site diversion around the project area.  

Project Timeline:

April 2025 - Nov. 2025

Alternate Route:

mina-detour.png

Project Updates:

Aug. 18, 2025: 

July 15–Aug. 15, 2025, Completed work: Crews completed the pier columns and cap, built the concrete abutment 1, and drove piles for abutment 2.

Anticipated work Aug. 15–Sept. 15, 2025: Crews plan to finish abutment 2, set the concrete girders, and begin forming the concrete deck. Work will also take place under the bridge to stabilize the channel.

Project Photos:

Project Contract Amount:

$5.7 Million

Project Contacts:

SDDOT: 
Robert Ward
605-626-7885

Contractor: 
RR Schroeder Construction, Inc.of Glenwood, MN.