U.S. Highway 12 - Between Aberdeen and Mina

4.png
Project Summary:

This project consists of a bridge replacement over Snake Creek. 


Traffic on Highway 12 will be directed to use the on-site diversion around the project area.  

Project Timeline:

April 2025 - Nov. 2025

Alternate Route:

mina-detour.png

Project Updates:

Oct. 31, 2025: 

Sept. 15, 2025 – Oct. 15, 2025, Completed Work: The contractor finished forming the deck and placing deck concrete. Drainage pipes have been installed, and the abutments and east sleeper slabs have been backfilled.

Anticipated Work Oct. 15, 2025 – Nov. 15, 2025: The contractor plans to finish forming and pouring the approach slabs and barriers. Asphalt approaches are also expected to be completed.

Project Photos:

Project Contract Amount:

$5.7 Million

Project Contacts:

SDDOT: 
Robert Ward
605-626-7885

Contractor: 
RR Schroeder Construction, Inc.of Glenwood, MN.