S.D. Highway 34 - Colman

Colman.png

Project Summary:

S.D. Highway 34 from West of 469th Ave to the East city limits of Colman. 

Project will include removal and replacement of PCC surfacing, constructing three-lane roadway to reduce rear end crashes through town. Project will also include storm sewer and shared use path.

  • Grading
  • Cement Concrete Surfacing
  • Shared Use Path

Sign Up for Text Notifications:

For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time. 

Text Colman34 to 605-566-4041

Project Timeline:

March 18, 2025 - May 2026

Project Updates:

Nov. 21, 2025: 

Oct. 15, 2025 – Nov. 15, 2025, Completed Work:
Work included completing the sidewalk and roadway lighting on the north side of Highway 34. The contractor also installed permanent signing, applied temporary pavement markings, performed final grading and topsoil placement, and finished permanent seeding.

Anticipated Work Nov. 15, 2025 – Dec. 15, 2025:
The project is complete, with the exception of permanent pavement markings, which will be placed in spring 2026.

Project Photos:


Project Contract Amount:

$10.3 Million

Project Contacts:

SDDOT: 
Bridger Kraye
605-940-1879


Contractor:
Hulstein Excavating Inc.
Pat McKnight
605-759-8656

STATEWIDE CONSTRUCTION PROJECTS PAGE

 

 

PCN: 0609