S.D. Highway 25 Resurfacing Near Willow Lake

WillowLake.png

Project Summary:

S.D. Highway 25 from North Junction S.D. Highway 28 north six miles.

  • Asphalt Concrete Surfacing


Project Timeline:

April 2025 - Nov. 2025

Project Updates:

July 22, 2025: 

On Wednesday, July 23, 2025, paving operations are scheduled to begin on S.D. Highway 25 near Willow Lake from just north of the S.D. Highway 28 junction north for six miles.
Traffic will be carried through the work zone with the use of flaggers and a pilot car. Motorists should expect delays of up to 15 minutes through the work area.
Paving operations are anticipated to be completed within three weeks.

---

July 22, 2025: 

June 15, 2025 – July 15, 2025, Completed Work: To date initial project staking and signage has been installed along the extents of S.D. Highway 25 North of S.D. Highway 28 in anticipation of initial pavement grinding and large-scale asphalt pavement placement operations that are to commence July 23, 2025, as of this writing. 

Anticipated work July 15, 2025 – Aug. 15, 2025: Pavement operation and the closures withing this portion of S.D. Highway 25 will begin July 23, 2025, and will be running 6 days a week, weather depending, for approximately three weeks. It is anticipated that the final striping and finishes to the roadway will be completed approximately mid August. 


Project Photos:



Project Contract Amount:

Coming Soon

Project Contacts:

SDDOT: 
Brad Letcher
605-353-7140


Contractor:

STATEWIDE CONSTRUCTION PROJECTS PAGE

 

 

PCN: 06YW