S.D. Highway 25 Resurfacing Near Willow Lake

WillowLake.png

Project Summary:

S.D. Highway 25 from North Junction S.D. Highway 28 north six miles

  • Asphalt Concrete Surfacing


Project Timeline:

April 2025 - Nov. 2025

Project Updates:

The project is currently under a 6 ton/axle load limit due to the temporary surfacing. The asphalt contractor is tentatively scheduled to start work in mid-July 2025.


Project Photos:



Project Contract Amount:

Coming Soon

Project Contacts:

SDDOT: 
Brad Letcher
605-353-7140


Contractor:

STATEWIDE CONSTRUCTION PROJECTS PAGE

 

 

PCN: 06YW