S.D. Highway 25 in Clark County Near Bradley

ClarkCountyNearBradley.png

Project Summary:

S.D. Highway 25 from nine miles north of U.S. Highway 212 to four miles north of S.D. Highway 20 (Clark/Day county Line)

  • Grading
  • Interim Surfacing
  • Pavement Marking

Project Timeline:

April 2025 - June 2026

Detour Maps:

highway25-cardetour.png

Project Updates:

Aug. 27, 2025: 

July 15, 2025 – Aug. 15, 2025, Completed Work:
S.D. Highway 25 remains closed for six miles south of S.D. Highway 20. The contractor continued grading operations to the south and began installing concrete pipe culverts beneath the roadway. Paving preparations also started, with topsoil placement and other finishing work underway at the northern end of the project.

Anticipated Work Aug. 15, 2025 – Sept. 15, 2025:
The contractor is expected to continue grading and installing concrete pipe culverts to the south. Finishing work and asphalt paving will follow as site conditions and weather allow.

Project Photos:



Project Contract Amount:

$11 Million

Project Contacts:

SDDOT: 
Brad Letcher
605-353-7140


Contractor:
Midwest Contracting LLC of Marshall, MN