S.D. Highway 25 in Clark County Near Bradley
Project Summary:
S.D. Highway 25 from nine miles north of U.S. Highway 212 to four miles north of S.D. Highway 20 (Clark/Day county Line)
Grading
Interim Surfacing
Pavement Marking
Paving
Detour Maps:
Project Updates:
April 15, 2026 - Press Release:
On Tuesday, April 21, 2026, crews will begin grading work on S.D. Highway 25 from S.D. Highway 20 north for approximately four miles. The grading work will require this four-mile section of Highway 25 to be closed to all through traffic.
The closure is anticipated to be in place until Saturday, Aug. 1, 2026. All truck traffic is required to use State highways to detour around the closure. Truck traffic detour routes includes Highway 20, Interstate 29, and U.S. Highway 12. No truck traffic will be permitted on 437th Avenue (Codington County Road 27) or 155th Street during the closure.
A passenger vehicle detour will also be provided using Highway 20, 437th Avenue (Codington County Road 27), and 155th Street.
Project Photos:
Schedule:
April 2025 - Fall 2026
Location:
S.D. Highway 25 from nine miles north of U.S. Highway 212 to four miles north of S.D. Highway 20 (Clark/Day Co Line)
Benefits:
Grading
Interim Surfacing
Pavement Marking
Paving
Estimated Cost:
Grading: $11 Million
Paving: $5 Million
Contractor:
Grading: Midwest Contracting LLC of Marshall, MN
Paving: Bituminous Paving, Inc
PCN: 04EW & 09VF
STATEWIDE CONSTRUCTION PROJECTS PAGE
© 2026 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
Region & Area Offices
Travelers
© 2026 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic