S.D. Highway 13 Near Elkton
Project Summary:
S.D. Highway 13 - From S.D. Highway 324 to U.S. Highway 14
- Shoulder Widening
- Resurfacing
- Approach Grading
- Pipe Work
- New Signal
Project Timeline:
April 2025 - November 2025
Project Updates:
June 25, 2025:
May 15, 2025 – June 15, 2025, Completed Work: The contractor continued grading operations on the east and west sections of S.D. Highway 13. They also installed new pipe at field approaches, intersecting roads, and entrances.
Anticipated work June 15, 2025 – July 15, 2025: The contractor will continue grading on the east and west sections of S.D. Highway 13. They will begin work on bridge removal and box culvert replacement on the north and south sections of the project.
---
April 30, 2025 - Press Release:
Construction Work has begun on S.D. Highway 13 from the intersection of S.D. Highway 324 toward the city of Elkton. Work on the project will include shoulder widening, asphalt concrete resurfacing, pipe work, grading and structure replacement. Lane closures will be in place for the project during the day. Traffic will be guided through the work zone with flaggers and a pilot car. Motorists should be prepared for delay through the work zone.
As part of this reconstruction project, Highway 13 is closed north of Elkton to U.S. Highway 14. A signed detour route is in place to guide traffic around the closed portion of Highway 13 using local roadways.
Project Photos:
Project Contract Amount:
$8 Million
Project Contacts:
SDDOT:Thomas Lindstrom
605-881-7137
Contractor:
R and G Construction Co.
507-537-1473
STATEWIDE CONSTRUCTION PROJECTS PAGE
PCN: 05EX
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
Region & Area Offices
Travelers
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic