S.D. Highway 10 - Between Britton and Houghton

2.png
Project Summary:

This project consists of widening the shoulder of the roadway to improve safety and will include a structure and pipe replacement. Additionally, the intersection will be modified at the turn lane.

Project Timeline:

Summer 2024 - Fall 2025

Project Updates:

May 20, 2025: 

May 15, 2025 – June 15, 2025, Completed Work: The contractor continued shoulder widening operations. They also striped topsoil, place contractor furnished borrow, granular material, and erosion control measures.    

Anticipated work in June 15, 2025 – July 15, 2025: The contractor will continue shoulder widening operations. They will also continue to strip topsoil, place contractor furnished borrow, granular material, and erosion control measures. They also plan to begin box culvert construction. 

 

Project Photos:


Project Contract Amount:

$4.8 Million

Project Contacts:

SDDOT: 
Robert Ward
605-626-7885

Contractor: 
RR Schroeder Construction, Inc. of Glenwood, MN