S.D. Highway 10 - Between Britton and Houghton

2.png
Project Summary:

This project consists of widening the shoulder of the roadway to improve safety and will include a structure and pipe replacement. Additionally, the intersection will be modified at the turn lane.

Project Timeline:

Summer 2024 - Fall 2025

Project Updates:

Aug. 18, 2025: 

July 15–Aug. 15, 2025, Completed Work: Crews widened shoulders, stripped topsoil, placed contractor-furnished borrow and granular material, completed pipe work, and installed erosion control measures. The subcontractor built box culverts.

Anticipated work Aug. 15–Sept. 15, 2025: Crews will continue shoulder widening, topsoil stripping, borrow and granular placement, pipe work, and erosion control. The subcontractor will continue box culvert construction.

Project Photos:


Project Contract Amount:

$4.8 Million

Project Contacts:

SDDOT: 
Robert Ward
605-626-7885

Contractor: 
RR Schroeder Construction, Inc. of Glenwood, MN