S.D. Highway 10 - Between Britton and Houghton

2.png
Project Summary:

This project consists of widening the shoulder of the roadway to improve safety and will include a structure and pipe replacement. Additionally, the intersection will be modified at the turn lane.

Project Timeline:

Summer 2024 - Fall 2025

Project Updates:

October 2024

Sept. 15, 2024 – Oct. 15, 2024, Completed Work: The contractor hauled borrow material for shoulder construction. They also continued extending pipe. 

Anticipated work Oct. 15, 2024 – Nov. 15, 2024: The contractor will continue hauling borrow material for shoulder construction and extending pipe. The contractor started placing granular material on shoulders in first three miles of construction.  


Project Photos:

Coming Soon


Project Contract Amount:

$4.8 Million

Project Contacts:

SDDOT: 
Robert Ward
605-626-7885

Contractor: 
RR Schroeder Construction, Inc. of Glenwood, MN