S.D. Highway 10 - Between Britton and Houghton

2.png
Project Summary:

This project consists of widening the shoulder of the roadway to improve safety and will include a structure and pipe replacement. Additionally, the intersection will be modified at the turn lane.

Project Timeline:

Summer 2024 - Fall 2025

Project Updates:

April 15, 2025:

March 15, 2025 – April 15, 2025, Completed Work: The contractor will be removing existing riprap along the shoulder of the project and hauling to stockpile.   

Anticipated work April 15, 2025 – May 15, 2025: The contractor will start constructing traffic diversions for box culvert replacements, stripping topsoil for grading operations, pipe culvert replacement and extensions, and begin to mill the asphalt concrete shoulder. 

---  

Project Photos:


Project Contract Amount:

$4.8 Million

Project Contacts:

SDDOT: 
Robert Ward
605-626-7885

Contractor: 
RR Schroeder Construction, Inc. of Glenwood, MN