S.D. Highway 10 - Between Britton and Houghton

2.png
Project Summary:

This project consists of widening the shoulder of the roadway to improve safety and will include a structure and pipe replacement. Additionally, the intersection will be modified at the turn lane.

Project Timeline:

Summer 2024 - Fall 2025

Project Updates:

June 20, 2025: 

May 15, 2025 – June 15, 2025, Completed Work: The contractor will continue shoulder widening operations, stripping topsoil, placing contractor furnished borrow, granular material, pipe work, and erosion control measures. The subcontractor began building box culverts. 

Anticipated work June 15, 2025 – July 15, 2025: The contractor will continue shoulder widening operations, stripping topsoil, placing contractor furnished borrow, granular material, pipe work, and erosion control measures. The subcontractor will continue building box culverts. 

 

Project Photos:


Project Contract Amount:

$4.8 Million

Project Contacts:

SDDOT: 
Robert Ward
605-626-7885

Contractor: 
RR Schroeder Construction, Inc. of Glenwood, MN