Rapid City - Anamosa Street Bridge I-190



Project Summary:

The project consists of:
- Replacing aged structure with weight restrictions
- Replacing and improving intersections at both ends of the bridge
- Reducing light pollution in communities adjacent to Interstate 190

The purpose of this project is to replace the Anamosa Street Bridge over Interstate 190 due to aging and weight restrictions. There will be luminaires replaced along the I-190 corridor that will provide reduced light pollution for the surrounding neighborhoods. A small section of concrete paving will occur on the north end of the I-190 structure and North Street including a barrier wall and glare screen.

Project Timeline:

Spring 2024 - July 2025

Project Pedestrian Detour:



Project Updates: 

June 17, 2025: 

At 5 a.m. (MT) on Saturday, June 21, 2025, the final temporary closure on Interstate 190 and exit 57 in Rapid City is scheduled to take place. Both I-190 and exit 57 are scheduled to reopen on Sunday, June 22, 2025, at 8 p.m. (MT). This closure allows crews to remove the temporary pedestrian crossing and falsework under the Anamosa Street Bridge over I-190. A signed detour route will be provided for motorists around the closure utilizing exit 55 (Deadwood Avenue), exit 61 (U.S. Highway 16B), and S.D. Highway 44 (Omaha Street).

When the roadway is reopened on Sunday, June 22, 2025, two-way traffic will be placed in the northbound lanes of I-190 to continue work on the structure. This closure is part of an ongoing bridge replacement project that consists of mainline work on I-190 and replacement of the Anamosa Street Bridge.

---

June 15, 2025:

June Completed Work: The contractor completed backfilling and pouring the approach slabs at both ends of the bridge. The contractor continued removing the falsework under the bridge pouring the sidewalks at both ends of the bridge. The contractor continued to install the barrier fence on the Anamosa bridge.  

Anticipated work in July: The contractor will move pedestrian traffic onto the Anamosa bridge and remove the temporary pedestrian bridge and footings. Traffic will be transferred into there respective sides of Interstate 190 and out of two-way configuration traffic. The contractor will finish the Anamosa Street bridge and open it to vehicle traffic. The contractor will remove the crossovers at each end of the project. Then they will begin removal and installation of the final light poles on I-190 and installing pavement markings. 

Project Photos:

 

 

Project Contract Amount:

$10.6 Million

 
Project Contacts:

Contractor: 
Heavy Constructors
David Dailey
605-381-8127

SDDOT:
Project Engineer
Justin Smith 
605-381-4035 