Interstate 90 - Exit 406 (Brandon)



Project Summary:

This project includes the reconstruction of exit 406 (Brandon) with added lighting, signals, and mainline Interstate work. This project also includes three structure replacements. 

  • The interchange will be reconstructed as a diverging diamond configuration.
  • Westbound Interstate 90 lanes (along with the railroad structure on I90) will be reconstructed in 2024 and the eastbound lanes (and railroad structure in 2025). The interchange itself and new structure over I90 will be reconstructed between 2024 and 2025.
  • S.D. Highway 11 traffic will be maintained across Interstate 90 during construction.
  • The westbound on-ramp and eastbound off-ramp are expected to be open to traffic for the majority of the project. Closures for the westbound off-ramp and eastbound on-ramp are planned for 2025.
  • Work will extend on S.D. Highway 11 down to Redwood Boulevard. That work includes adding a shared use path on the west side, approach and side street work, a retaining wall on the east side north of Ash St, and other items.


Sign Up for Text Notifications:

For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time. 

Text I90Exit406 to 605-566-4041


Project Timeline:

Spring 2024 - Overall Completion Date: June 2026

Minor clean-up work to be completed in 2026


Project Updates:

Dec. 19, 2024:

On Monday, Dec. 23, 2024, the westbound lanes of Interstate 90 at exit 406 (Brandon) are scheduled to be reopened. The traditional traffic configuration (two eastbound and two westbound lanes) will be in place throughout the winter months. It's anticipated that this traffic configuration will remain in place until phase two work begins in Spring 2025.

The traffic diversion on S.D. Highway 11 over the bridge at exit 406 will continue to have one northbound and one southbound lane open until the bridge is completed.

Access to businesses between exit 406 and Ash Street will remain as right turn-in and right turn-out only.

The remaining work on phase two of the project consists of completing the on-ramps and off-ramps, as well as the reconstruction of the eastbound lanes of I-90. The bridge at exit 406 and the bridge over the Burlington Northern Santa Fe Railroad will also be completed in phase two. Work is scheduled to resume in April 2025.

---

April 25, 2024:

March 26, 2024 - Dakota News Now: 


Watch the full story here

 

Project Resources (PDFs): 

Interstate 90 Layout

S.D. Highway 11 Layout

DDI Layout

Phasing Year One

Phasing Year Two


Project Photos:


Project Contract Amount:

$41.3 Million

Project Contacts:

SDDOT: 
Michael Noonan
605-940-1237

Contractor: 
T&R Contracting, Inc. of Sioux Falls, S.D.