Interstate 90 and I-29 and I-229 Bridges in Sioux Falls
Project Summary:
Interstate 90 East and West - Interstate 90 and Interstate 29 Interchange over I-29 drainage ditch and I-90/I-229 Interchange over I-229
- Bridge Deck Overlays
- Approach Slabs PCC Pavement
- Signing and Guardrail
Sign Up for Text Notifications:
For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time.
Text I90Bridges to 605-566-4041
Project Timeline:
April 2025 - Fall 2025
Project Updates:
July 8, 2025 - Press Release:
On Thursday, July 10, 2025, work will begin on the Interstate 90 westbound structure over Interstate 29. Traffic control will be put into place to allow for a two-way traffic configuration on eastbound I-90 utilizing crossovers. The north loop ramps of the I-90 and I-29 interchange will be closed during this time.
This two-way traffic configuration is anticipated to be in place until Friday, Aug. 15, 2025.
---
June 23, 2025:
May 15, 2025 – June 15, 2025, Completed Work:
Eastbound I-90 bridge over I-29
Work is now complete, and all lanes are back open along with the south loop ramps.
Westbound I-90 bridge over I-229
Two-way traffic is currently in place on eastbound I-90 to allow for work.
The contractor is currently working on removing delaminated concrete on the bridge deck.
Anticipated work June 15, 2025 – July 15, 2025: The contractor plans to complete low slump deck overlay, approach paving, mainline concrete paving, and guardrail work.
June 2, 2025:
On Tuesday, June 3, 2025, improvements to the westbound Interstate 90 bridge over Interstate 229 will begin. Crews will be placing traffic control to allow for two-way traffic on eastbound I-90 and closing the north loop ramps of the I-90 and I-229 interchange, exit 400.
Two-way traffic on eastbound I-90, along with the loop ramp closures, will be in effect from Thursday, June 5 until Friday, July 11, 2025.
Project Photos:
Project Contract Amount:
$3.1 Million
Project Contacts:
SDDOT:Brad Tiede
605-367-5680
Contractor:
Journey Group Companies
STATEWIDE CONSTRUCTION PROJECTS PAGE
PCN: 091T
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
Region & Area Offices
Travelers
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic