Interstate 90 and I-29 and I-229 Bridges in Sioux Falls

SiouxFallsBridges.png

Project Summary:

Interstate 90 East and West - Interstate 90 and Interstate 29 Interchange over I-29 drainage ditch and I-90/I-229 Interchange over I-229

  • Bridge Deck Overlays
  • Approach Slabs PCC Pavement
  • Signing and Guardrail

Sign Up for Text Notifications:

For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time. 

Text I90Bridges to 605-566-4041

Project Timeline:

April 2025 - Fall 2025

Project Updates:

July 8, 2025 - Press Release:

On Thursday, July 10, 2025, work will begin on the Interstate 90 westbound structure over Interstate 29. Traffic control will be put into place to allow for a two-way traffic configuration on eastbound I-90 utilizing crossovers. The north loop ramps of the I-90 and I-29 interchange will be closed during this time.  

This two-way traffic configuration is anticipated to be in place until Friday, Aug. 15, 2025.

---

June 23, 2025: 

May 15, 2025 – June 15, 2025, Completed Work:

Eastbound I-90 bridge over I-29 

Work is now complete, and all lanes are back open along with the south loop ramps. 

Westbound I-90 bridge over I-229 

Two-way traffic is currently in place on eastbound I-90 to allow for work. 

The contractor is currently working on removing delaminated concrete on the bridge deck. 

Anticipated work June 15, 2025 – July 15, 2025: The contractor plans to complete low slump deck overlay, approach paving, mainline concrete paving, and guardrail work.  

June 2, 2025: 

On Tuesday, June 3, 2025, improvements to the westbound Interstate 90 bridge over Interstate 229 will begin. Crews will be placing traffic control to allow for two-way traffic on eastbound I-90 and closing the north loop ramps of the I-90 and I-229 interchange, exit 400.

Two-way traffic on eastbound I-90, along with the loop ramp closures, will be in effect from Thursday, June 5 until Friday, July 11, 2025.


Project Photos:


Project Contract Amount:

$3.1 Million

Project Contacts:

SDDOT: 
Brad Tiede
605-367-5680


Contractor:
Journey Group Companies

STATEWIDE CONSTRUCTION PROJECTS PAGE

 

 

PCN: 091T