Interstate 29 Bridge Rehabilitation Sioux Falls - Over Skunk Creek
Project Summary:
Interstate 29 north and south - approximately ½ mile north of 26th Street over Skunk Creek, over 12th Street (exit 79), approximately ½ mile north of 12th Street over Ellis & Eastern Railroad.
- Bridge Deck Overlay
- Approach Slabs
- Guardrail
Project Timeline:
Spring 2025 - Fall 2025
Project Updates:
April 2, 2025 - Press Release:
On Monday, April 7, 2025, work will begin on the Interstate 29 northbound structures over 12th Street and the Ellis & Eastern Railroad tracks.
Traffic control will be in place closing the east two lanes. Traffic will be maintained on the two west lanes. This configuration will continue until Wednesday, May 21, 2025, when traffic will be switched to the newly constructed east lanes. Crews will then begin work on the adjacent two lanes on the west side.
Project Photos:
Project Contract Amount:
$7.4 Million
Project Contacts:
SDDOT:Brad Tiede
605-367-5680
Contractor:
General Excavating LLC.
STATEWIDE CONSTRUCTION PROJECTS PAGE
PCN: 065E
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
Region & Area Offices
Travelers
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic