City of Huron - S.D. Highway 37 (Dakota Ave.) 9th St. S. to 3rd St. N.

Project Summary:

The project consists of grading, paving, storm sewer, curb and gutter, traffic signals, and lighting.

Sign Up for Text Notifications:

For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time. 

Text HURON37 to 605-566-4041

Project Timeline:

May 2024 - The interim project completion date for 5th Street to Market Street is Nov. 2024, with an overall project completion date of Oct. 2025.

 

Detour Maps:

(Car and Truck)

    


Project Updates:

March 18, 2024 - Press Release: 

On Wednesday, March 19, 2025, work will resume on the S.D. Highway 37 (Dakota Avenue) reconstruction project through Huron. The median on Dakota Avenue between U.S. Highway 14 and 3rd Street North will be removed to allow for temporary traffic operations.

On Monday, March 31, 2025, a road closure will be placed on Highway 37 in both directions from 7th Street South to 9th Street South. Traffic will be diverted by detours. Also at that time, traffic will be moved to a two-way configuration on the east side of Dakota Avenue from Market Avenue to Highway 14 allowing construction to begin on the west side of the road. The ongoing street scape project on Dakota Avenue is also scheduled to begin on Monday, March 31, 2025.

---

June 13, 2024: 

---

April 25, 2024 - Press Release: Basic project information was presented at the pre-construction meeting. The meeting provided information regarding the construction start date, schedule, and phases. MEETING PRESENTATION.PDF

 

Project Photos:


Project Contract Amount:

$19 Million

Project Contacts:

Contractor:
BX Civil & Construction, Inc. 

 
SDDOT: 
Project Engineer
Parker Riddle
605-353-7140