City of Huron - S.D. Highway 37 (Dakota Ave.) 9th St. S. to 3rd St. N.

Project Summary:

The project consists of grading, paving, storm sewer, curb and gutter, traffic signals, and lighting.

Sign Up for Text Notifications:

For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time. 

Text HURON37 to 605-566-4041

Project Timeline:

May 2024 - The interim project completion date for 5th Street to Market Street is Nov. 2024, with an overall project completion date of Oct. 2025.

Detour Maps:

(Car and Truck)     

huron-37-car-detour.png   

 


Project Updates:

Nov. 24, 2025: 

Oct. 15, 2025 – Nov. 15, 2025 Completed Work: All work on the southern and northern portions of Dakota Avenue (S.D. Highway 37) has been completed, and all lanes are open to traffic. This concludes construction activities within the City of Huron for the 2025 season.

Anticipated Work Nov. 15, 2025 – Dec. 15, 2025: No additional work is anticipated along Dakota Avenue in 2025 or 2026. Future reconstruction on Dakota Avenue South, between 9th and 21st streets, is scheduled for spring 2027.

Project Photos:

Project Contract Amount:

$19 Million

Project Contacts:

Contractor:
BX Civil & Construction, Inc. 

 
SDDOT: 
Huron Area Office 
605-353-7140