S.D. Highway 25 – From S.D. Highway 28 North Junction to Hamre Slough
Project Summary:
The project consists of grading and interim surfacing on S.D. Highway 25.
Project Timeline:
March 18, 2024 - Nov. 2024
Detour Map:
Car and Truck Detour Maps
Project Updates:
May 15, 2024:
April 15, 2024 – May 15, 2024, Completed Work: Grading and pipe work in the south two and one-half miles.
Anticipated work in May 15, 2024 – June 15, 2024: Surfacing south two and one-half miles.
---
April 3, 2024 - Press Release: On Monday, April 8, 2024, grading work is scheduled to begin on S.D. Highway 25 from the north junction of S.D. Highway 28 to Hamre Slough. The anticipated reconstruction schedule is to complete grading in sections. Depending on weather conditions, the south half will be graded from mid-April to early July and the north half graded from mid-July to early September.
The project will reconstruct approximately six miles of Highway 25. The project includes grading, pipe work, and interim surfacing. Highway 25 will be fully closed to through traffic during the project with a detour provided. Access to businesses and residents throughout the project will be maintained from the nearest mile line road during active construction.
Project Photos:
Project Contract Amount:
$6.9 Million