City of Huron - S.D. Highway 37 (Dakota Ave.) 9th St. S. to 3rd St. N.

Project Summary:

The project consists of grading, paving, storm sewer, curb and gutter, traffic signals, and lighting.

Sign Up for Text Notifications:

For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time. 

Text HURON37 to 605-566-4041

Project Timeline:

May 2024 - The interim project completion date for 5th Street to Market Street is Nov. 2024, with an overall project completion date of Oct. 2025.

Detour Maps:

(Car and Truck)     

huron-37-car-detour.png   

 


Project Updates:

Aug. 22, 2025

July 15, 2025 – Aug. 15, 2025, Completed Work:
Dakota Avenue South between 7th and 9th streets is open to vehicular traffic, except for large trucks, which must continue to use the detour. Traffic on Dakota Avenue North of Market Street was shifted into a new detour configuration to allow pavement demolition, water service work, and sewer installation.

Anticipated Work Aug. 15, 2025 – Sept. 15, 2025:
Water and sewer work will continue in the former northbound lanes of Dakota Avenue North and will remain in place during the State Fair. Once underground utilities are complete, new concrete paving will be installed if conditions allow. Minor electrical and other ancillary work will also occur along Dakota Avenue South with little to no interruption to through traffic.

---

April 25, 2024 - Press Release: Basic project information was presented at the pre-construction meeting. The meeting provided information regarding the construction start date, schedule, and phases. MEETING PRESENTATION.PDF

Project Photos:

Project Contract Amount:

$19 Million

Project Contacts:

Contractor:
BX Civil & Construction, Inc. 

 
SDDOT: 
Huron Area Office 