City of Huron - S.D. Highway 37 (Dakota Ave.) 9th St. S. to 3rd St. N.

Project Summary:

The project consists of grading, paving, storm sewer, curb and gutter, traffic signals, and lighting.

Sign Up for Text Notifications:

For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time. 

Text HURON37 to 605-566-4041

Project Timeline:

May 2024 - The interim project completion date for 5th Street to Market Street is Nov. 2024, with an overall project completion date of Oct. 2025.

 

Detour Maps:

(Car and Truck)

    


Project Updates:

April 9, 2025 - Press Release:

On Monday, April 14, 2025, railroad crossing replacement work is scheduled to begin north of Market Street in Huron. Due to this work, S.D. Highway 37 (Dakota Avenue) will be closed from Market Street to Commercial Street for approximately two weeks. Upon completion of the crossing replacement, the contractor will begin to place storm sewer across Dakota Avenue at 2nd Street North. During the storm sewer project, Dakota Avenue will be closed from 3rd Street North to south of 2nd Street North. Dakota Avenue will remain open from Market Street to 2nd Street North during these operations. 

The storm sewer project is anticipated to last an additional two weeks. A signed detour will be in place during the project directing motorists to 3rd Street South, Lincoln Avenue, and U.S. Highway 14. Traffic on Dakota Avenue will be fully restored once the project is complete. 

 ---

March 18, 2024 - Press Release: 

On Wednesday, March 19, 2025, work will resume on the S.D. Highway 37 (Dakota Avenue) reconstruction project through Huron. The median on Dakota Avenue between U.S. Highway 14 and 3rd Street North will be removed to allow for temporary traffic operations.

On Monday, March 31, 2025, a road closure will be placed on Highway 37 in both directions from 7th Street South to 9th Street South. Traffic will be diverted by detours. Also at that time, traffic will be moved to a two-way configuration on the east side of Dakota Avenue from Market Avenue to Highway 14 allowing construction to begin on the west side of the road. The ongoing street scape project on Dakota Avenue is also scheduled to begin on Monday, March 31, 2025.

---

June 13, 2024: 

---

April 25, 2024 - Press Release: Basic project information was presented at the pre-construction meeting. The meeting provided information regarding the construction start date, schedule, and phases. MEETING PRESENTATION.PDF

 

Project Photos:


Project Contract Amount:

$19 Million

Project Contacts:

Contractor:
BX Civil & Construction, Inc. 

 
SDDOT: 
Project Engineer
Parker Riddle
605-353-7140