U.S. Highway 212 in Spink County near Frankfort
Project Summary:
U.S. Highway 212 from five miles east of Redfield to Doland
Project Updates:
June 29, 2026:
Anticipated Work in July 2026:
Asphalt milling and resurfacing of the roadway and shoulders will continue from Doland toward the bridge over Timber Creek and from approximately 3 miles east of Frankfort toward the bridge.
Final guardrail installation is anticipated to be completed in mid-July, marking the completion of the bridge rehabilitation work. Erosion control measures and permanent pavement markings will also be completed as the project enters its final phase, weather permitting.
Completed Work in June 2026:
The bridge over Timber Creek was resurfaced, and final paving operations were completed on U.S. Highway 212 west of Fisher Grove to approximately 2 miles east of Frankfort, including 396th Street and the Frankfort access road.
Milling operations began west of Doland, and blade-laid asphalt was placed in preparation for the final asphalt overlay on the roadway and shoulders.
Project Photos:
Schedule:
Grading: May 2025 - June 2026
Paving: Summer 2026 - Fall 2026
Location:
U.S. Highway 212 from five miles east of Redfield to east of Frankfort
Paving: U.S. Highway 212 five miles east of Redfield to Doland
Benefits:
Grading
Interim Surfacing
Pavement Markings
Asphalt Concrete Resurfacing
Bridge Approach Work
Final Surfacing
Estimated Cost:
Grading: $5.8 Million
Paving: $7 Million
Contractor:
Grading Contractor: Midland Contracting, Inc. of Volga, S.D.
Paving Contractor: Asphalt Paving & Materials, Co
PCN: 0808 & 06PQ
STATEWIDE CONSTRUCTION PROJECTS PAGE
© 2026 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
Region & Area Offices
Travelers
© 2026 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
