U.S. Highway 212 in Spink County near Frankfort

Frankfort active construction map

Project Summary:

U.S. Highway 212 from five miles east of Redfield to Doland

Project Updates:

April 29, 2026:

Anticipated work in May 2026: Structural steel and formwork operations are scheduled to continue on the west bridge approach slab, with work on the east bridge approach slab to follow. Once the approach slabs are placed and cured, crews will install pavement east and west of the bridge and install new guardrail. The work zone will continue to occupy the eastbound lane while crews complete excavation, drainage structure installation, and structural concrete work tying into the recently completed bridge approach slabs in the westbound lane.

Completed work in April 2026: The work zone detour and temporary signals were installed, and work began on Sunday, April 13, 2026. Excavation, drainage structure installation, and structural concrete sleeper slab placement have been completed. Reinforcing steel installation has begun on the west bridge approach slab.
 

Project Photos:

Schedule:

  • Grading: May 2025 - June 2026

  • Paving: Summer 2026 - Fall 2026

Location:

  • U.S. Highway 212 from five miles east of Redfield to east of Frankfort

  • Paving: U.S. Highway 212 five miles east of Redfield to Doland

Benefits:

  • Grading

  • Interim Surfacing

  • Pavement Markings

  • Asphalt Concrete Resurfacing

  • Bridge Approach Work

  • Final Surfacing

Estimated Cost:

  • Grading: $5.8 Million

  • Paving: $7 Million

Contractor:

  • Grading Contractor: Midland Contracting, Inc. of Volga, S.D.

  • Paving Contractor: Asphalt Paving & Materials, Co

PCN: 0808 & 06PQ

STATEWIDE CONSTRUCTION PROJECTS PAGE