U.S. Highway 212 in Spink County near Frankfort
Project Summary:
U.S. Highway 212 from five miles east of Redfield to Doland
Project Updates:
April 29, 2026:
Anticipated work in May 2026: Structural steel and formwork operations are scheduled to continue on the west bridge approach slab, with work on the east bridge approach slab to follow. Once the approach slabs are placed and cured, crews will install pavement east and west of the bridge and install new guardrail. The work zone will continue to occupy the eastbound lane while crews complete excavation, drainage structure installation, and structural concrete work tying into the recently completed bridge approach slabs in the westbound lane.
Completed work in April 2026: The work zone detour and temporary signals were installed, and work began on Sunday, April 13, 2026. Excavation, drainage structure installation, and structural concrete sleeper slab placement have been completed. Reinforcing steel installation has begun on the west bridge approach slab.
Project Photos:
Schedule:
Grading: May 2025 - June 2026
Paving: Summer 2026 - Fall 2026
Location:
U.S. Highway 212 from five miles east of Redfield to east of Frankfort
Paving: U.S. Highway 212 five miles east of Redfield to Doland
Benefits:
Grading
Interim Surfacing
Pavement Markings
Asphalt Concrete Resurfacing
Bridge Approach Work
Final Surfacing
Estimated Cost:
Grading: $5.8 Million
Paving: $7 Million
Contractor:
Grading Contractor: Midland Contracting, Inc. of Volga, S.D.
Paving Contractor: Asphalt Paving & Materials, Co
PCN: 0808 & 06PQ
STATEWIDE CONSTRUCTION PROJECTS PAGE
© 2026 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
Region & Area Offices
Travelers
© 2026 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
