S.D. Highway 1889 - Euclid Ave
Project Updates:
April 22, 2026:
On Saturday, April 25, 2026, the intersection of Highland Avenue and Wynoka Street is scheduled to re-open. The intersection will be surfaced with gravel until Wynoka Street is paved from Euclid Avenue to east of Evans Street in May 2026.
In order to complete construction on Wynoka Street, the following closures will be in place:
Wynoka Street will be closed from Euclid Avenue east to the Catholic Church entrance;
Wynoka Street will be closed from Highland Avenue east through Evans Street; and
The intersection of Wynoka Street with Mary Lane and Evans Street will be closed.
Euclid Avenue will continue to be closed north of the Euclid Avenue and Broadway Avenue intersection.
Commuters are encouraged to utilize alternative routes.
---
April 17, 2026:
Anticipated Work - May 2026:
On Euclid Avenue (from Broadway Avenue through Elizabeth Street):
Water line and storm sewer installation will continue. Undercut work will be completed, and base course placement may begin at Wynoka Street and continue north.
On Euclid Avenue (from Elizabeth Avenue to Fourth Street):
The traffic signals at Elizabeth Street will be removed. There is currently no work in this segment. The road is closed to westbound Elizabeth Street to accommodate the installation of new city sewer and sanitary lines. Because the west half of the Elizabeth intersection is closed for waterline and sanitary sewer installation, traffic will free-flow adjacent to the intersection work from Euclid Avenue east onto East Elizabeth Street.
On Euclid Avenue (from Fourth Street north to the divided four-lane north of Eighth Street):
Traffic control will continue with two-way traffic in the southbound lanes. Storm sewer placement will be underway between Fourth Street and Sixth Street in the northbound lanes. Backfill and subgrade compaction will also be underway. The contractor may then continue surfacing removal through Eighth Street.
On Wynoka Avenue (from Euclid Avenue east to Hilgers Gulch):
The Highland Avenue intersection will be closed as storm sewer construction begins across Highland Avenue. Storm sewer placement will continue toward Euclid Avenue. Highland Avenue will then be reopened and gravel surfacing placed.
On Elizabeth Avenue (from Grand to Euclid):
This one-block segment will remain closed as the City of Pierre continues sanitary sewer and new water line installation.
--
April 2026 - Completed Work:
Work resumed Monday, March 2, 2026. A 10-foot width restriction is in place for segments with two-way traffic. A detour is in place from the U.S. Highway 14/S.D. Highway 1889 intersection at Sioux and Pierre streets to the S.D. Highway 1804/Highway 1889 intersection north of Pierre.
On Euclid Avenue, from Broadway Avenue through Elizabeth Street, the roadway was closed the week of March 9. Traffic signals at Broadway Avenue were placed in flash. Surfacing, along with curb and gutter, was removed. All trees that conflicted with new construction were removed. Utility companies began relocating facilities in front of the new construction. The contractor has completed storm sewer and water line installation from Wynoka through Oak Street.
On Euclid Avenue, from Elizabeth Avenue to Fourth Street, no work is occurring in this segment except for traffic control on the north side of Elizabeth Street and the south side of Fourth Street. The road is closed on the south side of Elizabeth Street, and a T intersection is in place. A four-way stop was installed at Fourth Street.
On Euclid Avenue, from Fourth Street north to the divided four-lane section north of Eighth Street, traffic control was installed for two-way traffic in the southbound lanes. A crossover was built in the divided four-lane section north of Eighth Street. The contractor removed surfacing in the northbound lanes between Fourth and Seventh streets. Utility companies began relocating infrastructure to accommodate construction. Undercut has been removed.
On Wynoka Avenue, from Euclid Avenue east to Hilgers Gulch, the contractor removed surfacing and completed storm sewer installation from Highland Avenue to Hilgers Gulch.
--
April 7, 2026:
Beginning at 6 a.m. on Wednesday, April 8, 2026, the intersection of Highland Avenue and Wynoka Street is scheduled to close for new storm sewer installation. The closure is anticipated to be in place for three weeks.
Commuters will need to utilize alternative routes during this planned closure.
--
April 1, 2026:
Elizabeth Street closed from Grand Avenue to Euclid Avenue. Please see the linked presentation for details: https://dot.sd.gov/media/kqpbz20a/4_01_2026-euclid-public-meeting.pdf
2026 Construction Schedule:
Project Summary:
Urban reconstruction, asphalt and concrete surfacing, storm sewer, lighting, signals, sanitary sewer and water main replacement.
U.S. Highway 14/83 (Euclid Avenue) – from Sioux Avenue intersection to the divided highway west of S.D. Highway 1804 in Pierre.
Elizabeth Street (between Highway 14 and Grand Avenue).
Wynoka Street drainage outfall.
Sign Up for Text Notifications:
For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time.
Text EUCLID to 605-566-4041


