Euclid Ave in Pierre Construction Map


Project Updates:

June 26, 2026:

As of Friday, June 26, 2026, the south side of the Euclid Avenue and Fourth Street intersection in Pierre is reopened. On Monday, June 29, 2026, the east leg of Euclid Avenue and Fourth Street intersection is scheduled to be closed until mid-July 2026.

June 24, 2026:

View the weekly meeting presentation (PDF) 

June 10, 2026:

Beginning the week of June 15th, 2026, the south leg of the Euclid Avenue and Fourth Street intersection in Pierre will be closed for three weeks. The closure is to accommodate utility adjustments necessary for the Euclid Avenue reconstruction project. Commuters will need to utilize alternative routes during the closure.

View Updated Maps and Project Info Here

2026 Construction Schedule: 

Euclid Ave 2026 construction schedule and map

 

Project Summary:

Urban reconstruction, asphalt and concrete surfacing, storm sewer, lighting, signals, sanitary sewer and water main replacement.

  • U.S. Highway 14/83 (Euclid Avenue) – from Sioux Avenue intersection to the divided highway west of S.D. Highway 1804 in Pierre.​

  • Elizabeth Street (between Highway 14 and Grand Avenue).​

  • Wynoka Street drainage outfall.

Sign Up for Text Notifications:

For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time. 

Text EUCLID to 605-566-4041

 

Detour Map:

    Euclid Ave detour map


Project Photos:

Schedule:

  • Year One: Spring 2025 - Fall 2025

  • Year Two: Spring 2026 - Nov. 2026

Location:

  • S.D. Highway 1889 - Euclid Ave

Benefits:

  • Urban Grading

  • Curb and Gutter

  • Traffic Signals

Estimated Cost:

  • 26.4 Million

Contractor:

  • Morris Inc.

PCN: 026Z 