S.D. Highway 28 to S.D. Highway 15 East of Estelline

Estelline.png


Project Summary:

The project will replace and upgrade all drainage structures to improve overall drainage performance. The roadway will be fully regraded, cutting hills and filling valleys to enhance sight distance for drivers. In addition, the project will widen the shoulders along this segment to improve safety and accommodate future maintenance needs. The project will also include resurfacing the roadway.

  • Drainage Upgrades

  • Grading

  • Shoulder Widening

  • Surfacing

Sign Up for Text Notifications:

For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time. 

Text Estelline28 to 605-566-4041


Project Updates:

June 29, 2026:

Anticipated Work in July 2026:

Asphalt paving is anticipated to be completed around July 4, weather permitting. Following completion of paving, crews will install rumble strips, apply a flush seal, and place permanent pavement markings. All project work is anticipated to be completed in July.

Completed Work in June 2026:

The contractor completed the bottom and top lifts of asphalt paving east of Interstate 29 and the bottom lift of asphalt paving west of Interstate 29. Placement of the top lift west of Interstate 29 is anticipated to be completed within the next few weeks.

May 20, 2026: 

Anticipated work in June 2026: All roadway work for the grading project is anticipated to be complete in June. Remaining off-roadway punch list items will be completed as weather allows. Asphalt paving is anticipated to begin the week following Memorial Day.

Completed work in May 2026: The contractor completed prime application and chip seal east of Interstate 29 to finalize temporary surfacing. Most punch list items have been completed. Preparation for asphalt paving began west of Interstate 29, and temporary surfacing (prime application) was completed between Interstate 29 and the Peg Mucky Run Bridge.

Project Photos:

Schedule:

  • Grading: April 2025 - May 2026

  • Paving: June 2026 - Fall 2026

Location:

  • S.D. Highway 28 East of Estelline to S.D. Highway 15

Benefits:

  • Drainage Upgrades

  • Grading

  • Shoulder Widening

  • Surfacing

Estimated Cost:

  • Grading: $10.4 Million

  • Paving: 5.7 Million

Contractor:

  • Bowes Construction

PCN: 04HM

STATEWIDE CONSTRUCTION PROJECTS PAGE