S.D. Highway 28 to S.D. Highway 15 East of Estelline
Project Summary:
The project will replace and upgrade all drainage structures to improve overall drainage performance. The roadway will be fully regraded, cutting hills and filling valleys to enhance sight distance for drivers. In addition, the project will widen the shoulders along this segment to improve safety and accommodate future maintenance needs. The project will also include resurfacing the roadway.
Drainage Upgrades
Grading
Shoulder Widening
Surfacing
Sign Up for Text Notifications:
For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time.
Text Estelline28 to 605-566-4041
Project Updates:
April 17, 2026:
April 2026 Completed Work:
The contractor continued work on punch list items for the grading project and positive drainage. Crews also placed temporary pavement east of Interstate 29.
Anticipated Work – May 2026:
The contractor anticipates completing all remaining work on the grading project, with only punch list items remaining.
The paving project is expected to begin after Memorial Day and is scheduled for completion in early July.
Project Photos:
Schedule:
Grading: April 2025 - May 2026
Paving: June 2026 - Fall 2026
Location:
S.D. Highway 28 East of Estelline to S.D. Highway 15
Benefits:
Drainage Upgrades
Grading
Shoulder Widening
Surfacing
Estimated Cost:
Grading: $10.4 Million
Paving: 5.7 Million
Contractor:
Bowes Construction
PCN: 04HM
© 2026 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
Region & Area Offices
Travelers
© 2026 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
