Consultant Services
The South Dakota Department of Transportation uses the services of consulting engineers, architects, surveyors, and other specialists to perform work supplementing department forces or to provide services that the department is not staffed or equipped to do. Use of consultants allows the Department to accomplish our mission in an effective and timely way. Included on this page, you will find a variety of information including forms, guidelines, and other resources to help you provide transportation and consulting-related services which meet the guidelines of the SDDOT.
SDDOT maintains a consultant prequalification process in accordance with the Code of Federal Regulations 23 CFR Part 172. Every three years, SDDOT solicits interest from consultants for the prequalification process and addition to the retainer. Services are grouped into specific categories of work.
For specific projects, SDDOT requires consultants to be pre-qualified. For work not covered under any prequalification work type, consultants may utilize sub-consultants, at their discretion, with approval from SDDOT. PreQualification is not a guarantee of work. SDDOT is not obligated to award a contract or complete a project under this program.
Information for 2026-2028 Consultant Retainer Period
- Program work types
- Retainer list application resources - Step 1
- Retainer list selection resources - Step 2
GENERAL TIMELINE OF RETAINER PROCESS
- YEAR 1
- March
- Consultant Services Coordinator posts Requests For Qualifications
- Consultant Services Coordinator publishes notice for Statements of Interest in SD newspapers
- Consultant Services Coordinator updates SDDOT website
- June:
- Qualifications due from consultant
- July:
- Rankings due from selection committee; Retainer Board meets to approve
- August:
- Meet with Retainer Committee for final approval of selection lists
- Submit lists to Secretary for final approval
- Confirm that selected consultants are registered as corporations with the Secretary of State’s Office
- September:
- Consultant Services Coordinator notifies consultants whether they’ve been selected or not. Retainer Agreements will be attached to the selection email.
- October:
- Consultants send all retainer paperwork back to Consultant Services Coordinator
- December:
- Consultant Services Coordinator sends completed Retainer Agreement back to Consultant
- Retainer lists are updated on the SD DOT website
- March
INTERIM YEARS 2 AND 3
- May
- Consultant Services Coordinator posts Requests For Qualification
- Consultant Services Coordinator publishes notice for Statements of Interest in SD newspapers
- NOTE: Consultants may reapply for the categories they were not selected for the first go-round but MUST provide SIGNIFICANT improvement on the 925 form.
- July:
- Qualifications due from consultant
- August:
- Rankings due from selection committee; Retainer Board meets to approve
- Meet with Retainer Committee for final approval of selection lists
- Submit lists to Secretary for final approval
- Confirm that selected consultants are registered as corporations with the Secretary of State’s Office
- September:
- Consultant Services Coordinator notifies consultants whether they’ve been selected or not. Retainer Agreements will be attached to the selection email.
- October:
- Consultants send all retainer paperwork back to Consultant Services Coordinator
- December:
- Consultant Services Coordinator sends completed Retainer Agreement back to Consultant
- Retainer lists are updated on the SD DOT website
CURRENT LIST OF CONSULTANTS
Note: If the information listed for the specific Pre-Qualification Program work type is incorrect, please send an email to: tiffany.hanisch@state.sd.us
Disclaimer: Any outside entity relying on SDDOT’s Pre-Qualification Program lists to determine whether a firm is ‘qualified’ to perform that entity’s work should perform its own due diligence to determine and confirm the qualifications of any listed firm.
CONSULTANT SERVICES GUIDANCE
ADDITIONAL RESOURCES
Frequently Asked Questions
AUDITS
ELECTRONIC PLANS REVIEW FOR CONSULTANTS
QUESTIONS?
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
Region & Area Offices
Travelers
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic