March 21, 2024 - Nov. 2024
Sept. 20, 2024:
September Completed Work: The contractor completed the installation of bent two. They installed girders over the spans two, three, and four with falsework over the live northbound lane. They finished installing the H-pile for abutment one and grading for form work at both abutments. The concrete paving for the southbound lane north of the North Street bridge was completed. Asphalt was removed from Anamosa Street west of Nickel Street to complete grading operations. They will continue the installation of the median barrier and glare screen on I-190 at the Anamosa Street Bridge and north of the North Street Bridge. The contractor continued the installation of curb, gutter, asphalt, fence, and seeding operations on the west side of West Boulevard between stations. The end slope at span one of the Anamosa Street Bridge was graded with slope protection.
Anticipated work in October: The contractor will complete sawing, sealing, guard rail installation, and asphalt operations for paving operations north of the North Street bridge on the southbound lane. They will also complete the installation of girders for the Anamosa Street bridge for formwork to be installed. Both abutments will be completed after all the girders are installed. The contractor will complete the installation of the bridge deck along with the sidewalk and partial barrier curb. They will complete the installation of curb, gutter, and asphalt paving west of Nickel Street on Anamosa Street. They will complete the installation of median barrier and glare screen on I-190 at the Anamosa Street Bridge and north of the North Street Bridge. The contractor will complete the installation of curb, gutter, asphalt, fence, and seeding operations on the west side of West Boulevard between stations.
---
Sept. 3, 2024 - Press Release:
On Saturday, Sept. 7, 2024, the third of four temporary closures on Interstate 190 and exit 57 in Rapid City is scheduled to take place starting at 5 a.m. MT. Both I-190 and exit 57 are scheduled to reopen on Sunday, Sept. 8, 2024, at 8 p.m. MT. This closure allows crews to complete the installation of girders and falsework on the Anamosa Street Bridge over I-190. A signed detour route will be provided to motorists around the closure utilizing exit 55 (Deadwood Avenue), exit 61 (U.S. Highway 16B), and S.D. Highway 44 (Omaha Street).
When the roadway is reopened, two-way traffic will be placed in the northbound lanes of I-190.
---
Aug. 23, 2024 - Press Release:
On Wednesday, Aug. 28, 2024, the Anamosa Street and Nickel Street intersection in Rapid City will be temporarily closed to traffic. This temporary closure will allow crews to reconstruct the eastern half of the intersection, replace surfacing, and meet current ADA standards.
During the closure, one lane of traffic will be maintained on the north/south route of Nickel Street through the intersection. A signed detour route will be provided to motorists around the temporary closure utilizing Silver Street. The intersection is anticipated to be reopened by Monday, Sept. 30, 2024.