U.S. Highway 281 South of Aberdeen

U.S. Highway 281 South of Aberdeen Location Map

Project Summary:

The project includes placing a (LSDC)-Low Slump Dense Concrete overlay on the bridge deck to strengthen and protect the surface while improving ride quality.

Crews will also replace the approach slabs and resurface the approach pavement to provide a smoother transition on and off the bridge.

Project Updates:

May 20, 2026: 

Anticipated work in June 2026: Work will take place on the southbound and northbound twin bridges at mile marker 187.6. Activities include drainage installation, sleeper slabs, approach slabs, and new PCCP pavement on one side of each bridge.

Completed work in May 2026: A single-lane closure was in place. Crews set barriers, removed guardrails, milled bridge decks, placed deck overlays, and removed approach slabs.

Project Photos:

Schedule:

  • April 13, 2026 - Fall 2026

Location:

  • U.S. Highway 281 South of Aberdeen

Benefits:

  • Bridge Deck Overlay

  • Guardrail

  • Approach Surfacing

Estimated Cost:

  • $2.8 Million

Contractor:

  • Journey Group Companies

PCN: 0901