S.D. Highway 46 - From Beresford to Iowa State Line

Due to recent rains, please contact Foothills Construction at 1-605-216-0091 for access to property from nearest mile line.

Project Summary:

This project is a fifteen-and-one-half mile-long full reconstruction of S.D. Highway 46 in Union and Lincoln Counties. The project begins at the east edge of the city of Beresford and ends at the Iowa state line. Work on this project will consist of full roadway grading, structure replacement, culvert replacement, interim surfacing, and new permanent signing.

Construction is broken into three phases and covers two construction seasons.

Phase one starts at the east edge of Beresford and ends at the S.D. Highway 11/S.D. Highway 46 intersection. Work in phase one will be completed during the 2024 season with an interim completion date of Nov. 2024.

Phase two will be from the Highway 11/ Highway 46 intersection to the Hudson curve.

Phase three will be completed under traffic from the Hudson curve to the Iowa state line. Phase two and three will be completed during the 2025 construction season.

During construction, the highway will be closed to thru traffic. Access to residents and landowners adjacent to the project will be maintained, but travelers are encouraged to use the signed detour route around the project. The detour route around the project for phase one includes Interstate 29 to Lincoln County 152 and Highway 11. Phase two detour includes Highway 11 to Lincoln Co 152 and Lincoln Co 143. Phase three will be completed under traffic using temporary widening.

Sign Up for Text Notifications:

For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time. 

Text "BERESFORD46" to 605-566-4041


Project Timeline:

Spring 2024 - Nov. 2025

Project Updates:

April 26, 2024:

Due to recent rains, please contact Foothills Construction at 1-605-216-0091 for access to property from nearest mile line. 

---

April 15, 2024: 

March 15, 2024April 15, 2024, Completed WorkRoad was closed to through traffic on April 2, 2024. Began reclaiming existing asphalt pavement and gravel base from 472nd Avenue to 476th Avenue. Hauling stockpiling salvaged material to the stockpile site at the west end of the project. Stripping topsoil from 473rd Avenue to 476th Avenue 

Anticipated work in April 15, 2024May 15, 2024Heavy grading will start just west of 476th Avenue and proceed to the west. Installation of new pipe culverts will also start at 476th Avenue and work to the west. The remaining salvaged surfacing will be removed to the west end of the project. 

---

March 21, 2024 - Press Release

On April 3, 2024, S.D. Highway 46, from the east edge of the City of Beresford to S.D. Highway 11, is tentatively scheduled to close. The closure date will depend upon weather and road conditions along the project. During the closure, motorists will be directed to the signed detour route on Interstate 29, Lincoln County Highway 152, and Highway 11. Access to residences and properties adjacent to the project will be maintained for local traffic. Work to be completed during the first year of this two-year project includes full roadway grading, replacement of three structures, interim surfacing, and new signing from east of Beresford to Highway 11.

 

Project Detour Maps:

2024 Phase One Detour Map: 
Click to enlarge



Railroad Detour Map:
Click to enlarge



2025 Phase Two Detour Map: 
Click to enlarge


Project Photos:


Project Contract Amount:

$24.8 Million

Project Contacts:

SDDOT: 
Brian Wenisch
605-668-2929 x 1302005

Contractor:
Foothills Contracting of Webster, S.D.
605-345-3795


TransportationDoing Business
Certification & AccreditationContractorsEngineering/Design ServicesEnvironmentalLocal GovernmentsTraffic Incident Management
Projects & Studies
PlanningStudiesConstruction ProjectsSDDOT InnovationPublic Meetings
Programs & ServicesTravelersInside SDDOTDOT Fact BookBlogsHome test