Interstate 90 Bull Creek Bridges Near Wasta

 

Wasta.png

Project Summary:

  • Structure Work
  • Approach Grading
  • Surfacing

Project Timeline:

March 2025 - Spring 2026

Project Updates:

May 20, 2025: 

May Completed Work: The contractor completed the drilled shafts and columns for the westbound bridge. They will began piling work at the abutments and bent cap installation.  

Anticipated Work in June: The contractor will complete the pile installation at the abutments. They will also install steel, form, and pour the abutments and bent caps. The contractor may install girders and begin falsework. 


Project Photos:



Project Contract Amount:

$15 Million

Project Contacts:

SDDOT: 
Brenda Flottmeyer
605-394-1638


Contractor:
Heavy Constructors, Inc. from Rapid City, SD