Interstate 90 Bull Creek Bridges Near Wasta

Wasta.png


Project Summary:

  • Structure Work

  • Approach Grading

  • Surfacing

Project Updates:

June 29, 2026:

Anticipated Work in July 2026:

The contractor will complete grading operations on the roadway. Bridge approach work and sleeper slabs will be constructed. Asphalt paving will be completed.

Completed Work in June 2026:

The contractor completed deck placement and installation of stainless reinforcing steel. The bridge deck was poured June 10. Bridge end backfill and barrier construction were also completed.

Project Photos:

Schedule:

  • March 2025 - Aug. 2026

Location:

  • Interstate 90 Bull Creek Bridges Near Wasta

Benefits:

  • Structure Work

  • Approach Grading

  • Surfacing

Estimated Cost:

  • $15 Million

Contractor:

  • Heavy Constructors, Inc.

PCN: 035F