Interstate 90 Bull Creek Bridges Near Wasta

 

Wasta.png

Project Summary:

  • Structure Work
  • Approach Grading
  • Surfacing

Project Timeline:

March 2025 - Spring 2026

Project Updates:

Nov. 21, 2025: 

November Completed Work:
The contractor completed asphalt paving at the bridge ends. Rumble strips and permanent pavement markings were installed. The road and new bridge were opened to traffic on Nov. 7, 2025. Surfacing at the median crossover near MRM 105 was also replaced for use during the next phase of construction, anticipated to begin in March 2026, when the eastbound bridge over Bull Creek will be replaced.

Anticipated Work in December:
No work is anticipated until March 2026. Updates will be suspended until construction resumes.

Project Photos:



Project Contract Amount:

$15 Million

Project Contacts:

SDDOT: 
Jason Baker
605-394-2244

Contractor:
Heavy Constructors, Inc. from Rapid City, SD

STATEWIDE CONSTRUCTION PROJECTS PAGE

 

 

PCN: 035F