Interstate 90 Bull Creek Bridges Near Wasta

 

Wasta.png

Project Summary:

  • Structure Work
  • Approach Grading
  • Surfacing

Project Timeline:

March 2025 - Spring 2026

Project Updates:

June 25, 2025: 

June Completed Work: The contractor completed the bent caps, abutment pile driving, and poured the bottom of the abutments for the westbound bridge. Concrete girder installation began between abutment #1 and bent #2. Surfacing removal and undercutting was performed on the west end of the bridge. 

Anticipated Work in July: The contractor will complete the girder installation and begin falsework for the bridge deck. Grading will be completed, base course will be installed, and asphalt pavement will begin. 


Project Photos:



Project Contract Amount:

$15 Million

Project Contacts:

SDDOT: 
Brenda Flottmeyer
605-394-1638


Contractor:
Heavy Constructors, Inc. from Rapid City, SD