Interstate 90 Bull Creek Bridges Near Wasta
Project Summary:
Structure Work
Approach Grading
Surfacing
Project Updates:
May 20, 2026:
Anticipated work in June 2026: The contractor will complete bridge deck forming and reinforcing steel installation, place the bridge deck concrete, set forms and install reinforcing steel for the bridge barriers, and place the bridge barrier concrete. Granular backfill at the bridge ends will be installed, and sleeper slab and approach slab work will begin. Grading will continue in preparation for asphalt paving anticipated in late June to early July.
Completed work in May 2026: The contractor completed bent No. 2, placed the abutment footing for abutment No. 1, set girders for spans 1 and 2, and began bridge deck forming and installation of stainless reinforcing steel.
Project Photos:
Schedule:
March 2025 - Aug. 2026
Location:
Interstate 90 Bull Creek Bridges Near Wasta
Benefits:
Structure Work
Approach Grading
Surfacing
Estimated Cost:
$15 Million
Contractor:
Heavy Constructors, Inc.
PCN: 035F
STATEWIDE CONSTRUCTION PROJECTS PAGE
© 2026 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
Region & Area Offices
Travelers
© 2026 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic