Project Summary:

This project consists of widening the shoulder of the roadway to improve safety and will include a structure and pipe replacement. Additionally, the intersection will be modified at the turn lane. 

Phase two of the project will consist of milling and asphalt resurfacing. 

Project Updates:

May 20, 2026:

Anticipated work in June 2026: Asphalt concrete paving, striping, topsoil placement, seeding, and erosion control.

Completed work in May 2026: Grading, placement of granular material, milling, and topsoil placement and seeding.

Project Photos:

Schedule:

  • Grading Summer 2024 - Summer 2026

  • Paving - 2026

Location:

  • S.D. Highway 10 From Houghton to Britton

Benefits:

  • Shoulder widening to improve safety 

  • Intersection modification

  • Resurfacing

Estimated Cost:

  • Grading: $22.9 Million

  • Paving: $7.3 Million 

Contractor:

  • Grading: Loiseau Construction

  • Paving: Central Specialties, Inc. 

PCN: 05F4 & 06Q9