Project Summary:
Pipe repair and asphalt overlay.
Project Timeline:
April 17, 2023 - December 2023
Project Updates:
Nov. 22, 2023:
November Completed Work: The contractor spent the month finishing drainage grading, placing topsoil, gabion baskets, underdrains, headwalls, signs and delineators.
Anticipated Work in December: Seeding, Erosion Control, fencing, and punch list items to complete the project.
Project Photos:
Project Contract Amount:
$9.1 Million
Project Contacts:
Contractor:
Morris Inc.
The SDDOT Project Engineer:
Dan Vockrodt 605-773-2413