SIOUX FALLS, S.D. – The South Dakota Department of Transportation (SDDOT) says that bridge demolition will begin on Tuesday, Sept. 20, 2022, for the 60th Street Bridge over Interstate 229 just south of the I-90/229 interchange.

The contractor will begin bridge demolition during nighttime hours from 8 p.m. to 6 a.m.

During the demolition process, I-229 will be closed from the I-90 interchange to Benson Road in both directions. A detour route will be in place during the closure. The closure of I-229 is expected to take three nights, beginning Tuesday evening.

The prime contractor on the $6.5 million project is Grangaard Construction, Inc. of Watertown, S.D. The overall completion date for the project is Aug. 11, 2023.

Find additional information on the featured project site: https://dot.sd.gov/siouxfalls-pcn-01qa.


About SDDOT:
The mission of the South Dakota Department of Transportation is to efficiently provide a safe and effective public transportation system.

For the latest on road and weather conditions, road closures, construction work zones, commercial vehicle restrictions, and traffic incidents, please visit https://sd511.org or dial 511.

Read more about the innovative work of the SDDOT at https://dot.sd.gov.

-30-