U.S. Highway 85 - Ludlow to North Dakota State Line
Project Summary:
The project will include a full-depth reclamation, cold milling, asphalt concrete surfacing, and pipe work.
The project will increase the smoothness of highway surface by removing cracking, which will also improve the strength and stability of the highway.
Project Timeline:
March 12, 2024 - Nov. 2024
Project Updates:
April 15, 2024
March 15, 2024 – April 15, 2024, Completed Work: The contractor has been performing pipe work and will continue with the pipe work until completed.
Anticipated work in April 15, 2024 – May 15, 2024:The week of April 22, 2024, the contractor plans to begin the 1.5” milling process. After the milling process has been completed, the contractor will begin the Full Depth Reclamation (FDR) process.
Project Photos:
Project Contract Amount:
$8.5 Million