U.S. Highway 14 - From Midland to Four Corners Jct.
Project Summary:
This project consists of asphalt resurfacing, shoulder full-depth reclamation, and pipe work.
Project Timeline:
Spring 2024 - Nov. 2024
Project Updates:
March 15, 2024 – April 15, 2024, Completed Work: The contractor started work at the bridge over Mitchell Creek. They removed the existing steel rail and started the removal of concrete on the existing bridge curb on the south side of the bridge.
Anticipated work in April 15, 2024 – May 15, 2024: The contractor will continue removals on the bridge over Mitchell Creek and pour the jersey barrier on the south side of the bridge. They will flip traffic and begin work on the north side of that structure. They will begin work onthe bridge over Lone Tree Creek and the bridge over Little Prairie Dog Creek.
Project Photos:
Project Contract Amount:
$10.9 Million
Project Contacts: