Newell to Maurine - U.S. Highway 212

Project Summary:

The project is on US212 from Newell to Maurine, about 48 miles. The highlights of this project consist of 96 pipe repair sites, FDR, which is Full Depth Reclamation of the shoulders for certain sections of the roadway, and the placing of 125,000 tons +/- of asphalt concrete pavement.

The benefits include replacement of aged driving surface for a smoother ride, improved drainage and paved shoulders.

 

Project Timeline:

The project was let January 19, 2022 and the fieldwork completion date is November 18, 2022.

Project Updates: 

The contractor is scheduled to start the full width pipe replacement work on May 23, 2022. This work consists of sawing the asphalt surface, removing the asphalt surface, base material and existing pipe one half road width at a time to allow for traffic to pass through the work zone. The next steps include the installation of the new pipe and base material. The contractor is required to bring the base material up to the existing roadway elevation prior to the end of the day. This process will be repeated for the opposite side. After both sides have been completed, excess base material will be removed and replaced with asphalt to the existing surface elevation. There are five locations requiring this type of work. Traffic will be maintained with flaggers during working hours and open to traffic in the evenings with gravel surfacing until paved. This work needs to be completed prior to the final asphalt paving process.

 

Project Contract Amount:

$15.3 Million

 

Project Contacts:

Contractor: Anderson Western for Bismarck, ND. Jeremy Holt  (701) 222-3550 

The Project Engineer is Chris Bliss. (605) 892-2872.


2022 CONSTRUCTION PROJECTS PAGE



PCN 068V

TransportationDoing Business
Certification & AccreditationContractorsEngineering/Design ServicesEnvironmentalLocal Governments
Projects & Studies
PlanningStudiesConstruction ProjectsSDDOT InnovationPublic Meetings
Programs & ServicesTravelersInside SDDOTDOT Fact Book