Newell to Maurine - U.S. Highway 212

Project Summary:

The project is on US212 from Newell to Maurine, about 48 miles. The highlights of this project consist of 96 pipe repair sites, FDR, which is Full Depth Reclamation of the shoulders for certain sections of the roadway, and the placing of 125,000 tons +/- of asphalt concrete pavement.

The benefits include replacement of aged driving surface for a smoother ride, improved drainage and paved shoulders.

 

Project Timeline:

The project was let January 19, 2022 and the fieldwork completion date is November 18, 2022.

Project Updates: 

On April 20, 2022, a preconstruction meeting was held at the Belle Fourche Area office. The contractor is scheduled to start the pipework the beginning of June. The milling and full-depth reclamation is scheduled to begin the first week of August. The paving is scheduled to start shortly after the milling and full-depth reclamation processes and is anticipated to be completed by the end of September with the installation of the rumble strips, flush seal and permanent striping to follow.

 

Project Contract Amount:

$15.3 Million

 

Project Contacts:

Contractor: Anderson Western for Bismarck, ND. Jeremy Holt  (701) 222-3550 

The Project Engineer is Chris Bliss. (605) 892-2872.


2022 CONSTRUCTION PROJECTS PAGE



PCN 068V

TransportationDoing Business
Certification & AccreditationContractorsEngineering/Design ServicesEnvironmentalLocal Governments
Projects & Studies
PlanningStudiesConstruction ProjectsSDDOT InnovationPublic Meetings
Programs & ServicesTravelersInside SDDOTDOT Fact Book