Meade County - U.S. Interstate 90 Exit 37 (Pleasant Valley) to Exit 40 (Tilford)


Exit 37 Reconstruction, Eastbound Interstate 90 Grading and Paving, Commercial Vehicle Electronic Screening System, and New Port of Entry Building.


Exit 37 Reconstruction with new bridge overpass, exit ramps, and realignment of Pleasant Valley Road

Benefits:

  • Replace the aging overpass structure
  • Extend exit ramps for additional capacity
  • Increase safety with reduced skew of Pleasant Valley Road
The port of entry will be closed until the Fall of 2023.


Replacement of the Port of Entry

Benefits:

  • Replace the aging port of entry building.
  • Building improvements to allow for more thorough and sheltered inspections
  • New pavement surfacing and markings to improve site function

Project Summary:

The purpose of this project is to reconstruct the I90 Eastbound lanes from west of Exit 37 (Pleasant Valley Road) to the railroad multi-plate at MRM 38.34 and the westbound on-ramp and eastbound off-ramp at Exit 40 (Tilford) due to the pavement condition. This will also include replacing the interchange at Exit 37 (Pleasant Valley Road - structure# 47-061-480), PCC surfacing, and replacing all the pipe within the project limits under the EB lanes. Additionally, a new Tilford Port of Entry will be constructed including a new building, new parking lot, and new E-Screening infrastructure.

 

Project Timeline:

Spring 2022 - October 2023

Project Updates:

Sept. 21, 2023:

September Completed Work:  The contractor continued paving efforts at the Port of Entry. Grading work continued on the new alignment for Pleasant Valley Road, west of the railroad tracks. Finish grading, topsoil, and seeding occurred at various locations. Wildlife fence was installed at locations throughout the project and will continue as grading work is completed. The precast box culvert near Exit 40 was extended. The end of the box culvert near the Port of Entry on-ramp has been removed so that the box culvert can be extended. Paving of the eastbound on-ramp at Exit 37 has begun. Grading of Pleasant Valley Road on the east side of the new bridge has begun. The old Exit 37 bridge has been completely removed. Install base course on the new Pleasant Valley Road alignment in preparation for asphalt paving. Begin paving Pleasant Valley Road at the bridge ends. 

Anticipated work in October:  Continue grading, topsoil installation, and seeding throughout the project limits. Finish paving the eastbound ramps at Exit 37. Asphalt paving of the new Pleasant Valley Road alignment, west of the railroad tracks. Continue paving Pleasant Valley Road at the bridge ends. Finish PCC paving at the Port of Entry. Finish installing the commercial vehicle electronic screening infrastructure. Build the new deceleration lane for the eastbound off ramp at Exit 40. 

 

Project Photos:


November / December 2022:
(L to R: Asphalt and Concrete Paving on WB I-90, Paving the WB Acceleration Lane at Exit 37, Pouring the Columns of the Center Bent for the new Bridge at Exit 37)

  

October 2022:
(L to R: Exit 37 Ramp B Prepared for Pavement, Pouring the walls of the box culvert, Port of Entry building footings)
   

September 2022:

(L to R: Exit 37 Ramp B Grading, Removing a 3-10'x10’ box and Replacing with a 10’x20’ box,  Exit 37 Ramp C Grading)

  

July 2022: 
(L to R: Exit 37 Ramp B Grading, Pile Driving Exit 37 Bridge Center Bent, Pouring the footing for the Exit 37 Bridge Center Bent)

  


Project Timeline:

  • Bid Letting – May 4, 2022
  • Pre-Rally 2022
    • Grading work outside of the roadway
    • Temporary Guardrail/Temporary Barrier installation
    • Reconstruct Exit 40 WB on-ramp
      • The ramp will be closed with a detour to Exit 44.
      • Exit 40 Ramp A Detour
    • Begin substructure work for the new overpass bridge at Exit 37
  • No work affecting traffic July 27 – August 14, 2022
  • Post-Rally 2022 – I-90 Westbound Construction
    • Begin work to replace the port of entry
    • Two-way traffic in the EB lanes
    • Perform culvert replacements under the WB lanes
    • Complete box culvert work under the WB lanes
    • Complete commercial vehicle screening system work in the WB lanes
    • Complete the WB On and Off-Ramp at Exit 37
      • WB On-Ramp traffic will be detoured to Exit 40
      • Exit 37 Ramp A Detour
    • Continue structure work at the new Exit 37 overpass bridge.
  • No work is anticipated along the roadway between October 29, 2022, and March 20, 2023
  • Pre-Rally 2023 – I-90 Eastbound Construction
    • Complete the port of entry construction
      • Includes the replacement of the on/off ramps to the port of entry
    • Two-way traffic in the WB lanes
    • Complete all commercial vehicle screening system work in the EB lanes
    • Complete culvert replacements under the EB lanes
    • Complete box culvert work under the EB lanes
    • Grading work for the realignment of Pleasant Valley Road
    • Reconstruct Exit 40 EB Off Ramp
      • Ramp will be closed with a detour to Exit 44.
      • Exit 40 Ramp D Detour
  • No work affecting traffic July 29 – August 13, 2023
  • Post-Rally 2023 – Pleasant Valley Road Construction
    • Demolition of existing Exit 37 bridge
    • Complete the realignment/reconstruction of Pleasant Valley Road
    • Demolition of median crossovers
  • Project Completion October 27, 2023

Project Phasing Maps:

  • Phase 3 (Pre-Rally 2023)
  • Phase 4 (Post-Rally 2022)

 

 Project Contacts:

Contractor: Complete Concrete, Inc. dba Complete Contracting Solutions
605-388-0111

Contract Amount: $35 Million

SDDOT: Jason Baker 605-394-1629

 STATEWIDE CONSTRUCTION PROJECTS PAGE

TransportationDoing Business
Certification & AccreditationContractorsEngineering/Design ServicesEnvironmentalLocal Governments
Projects & Studies
PlanningStudiesConstruction ProjectsSDDOT InnovationPublic Meetings
Programs & ServicesTravelersInside SDDOTDOT Fact BookBlogsHome test