Meade County - U.S. Interstate 90 Exit 37 (Pleasant Valley) to Exit 40 (Tilford)


Exit 37 Reconstruction, Eastbound Interstate 90 Grading and Paving, Commercial Vehicle Electronic Screening System, and New Port of Entry Building.


Exit 37 Reconstruction with new bridge overpass, exit ramps, and realignment of Pleasant Valley Road

Benefits:

  • Replace the aging overpass structure
  • Extend exit ramps for additional capacity
  • Increase safety with reduced skew of Pleasant Valley Road
The port of entry will be closed until the Fall of 2023.


Replacement of the Port of Entry

Benefits:

  • Replace the aging port of entry building
  • Building improvements to allow for more thorough and sheltered inspections
  • New pavement surfacing and markings to improve site function


Project Summary:

The purpose of this project is to reconstruct the Interstate 90 eastbound lanes from west of exit 37 (Pleasant Valley Road) to the railroad multi-plate and the westbound on-ramp and eastbound off-ramp at exit 40 (Tilford) due to the pavement condition. This will also include replacing the interchange at exit 37 (Pleasant Valley Road), PCC surfacing, and replacing all the pipe within the project limits under the EB lanes. Additionally, a new Tilford Port of Entry will be constructed including a new building, new parking lot, and new E-Screening infrastructure.

 

Project Timeline:

Spring 2022 - June 2024

Project Updates:

April 3, 2024: On Wednesday, April 3, 2024, the remaining work on the project that reconstructed the exit 37 interchange on Interstate 90, near Sturgis, will begin. The remaining work includes pavement repairs in the eastbound lanes, concrete repairs on the westbound on and off-ramps at exit 37, concrete repairs on Pleasant Valley Road, median crossover construction for a future project that will reconstruct exit 34, smoothness grinding of the concrete pavement, pavement markings, storm sewer pipe cleaning, permanent signing, miscellaneous grading and seeding throughout the project limits, and overall project cleanup.

There will be a 16-foot width restriction in place and traffic will be limited to a single lane in each direction, with speed limits reduced to 65 mph through the work zone, and 45 mph when workers are present.

---

March 19, 2024:
The contractor will continue to install wildlife fencing and right-of-way fencing on Pleasant Valley Road and from Exit 37 to Exit 40 along the eastbound lanes of Interstate 90. 

Project Photos:


November / December 2022:
(L to R: Asphalt and Concrete Paving on WB I-90, Paving the WB Acceleration Lane at Exit 37, Pouring the Columns of the Center Bent for the new Bridge at Exit 37)

  

October 2022:
(L to R: Exit 37 Ramp B Prepared for Pavement, Pouring the walls of the box culvert, Port of Entry building footings)
   

September 2022:

(L to R: Exit 37 Ramp B Grading, Removing a 3-10'x10’ box and Replacing with a 10’x20’ box,  Exit 37 Ramp C Grading)

  

July 2022: 
(L to R: Exit 37 Ramp B Grading, Pile Driving Exit 37 Bridge Center Bent, Pouring the footing for the Exit 37 Bridge Center Bent)

  


Project Timeline:

  • Bid Letting – May 4, 2022
  • Pre-Rally 2022
    • Grading work outside of the roadway
    • Temporary Guardrail/Temporary Barrier installation
    • Reconstruct Exit 40 WB on-ramp
      • The ramp will be closed with a detour to Exit 44.
      • Exit 40 Ramp A Detour
    • Begin substructure work for the new overpass bridge at Exit 37
  • No work affecting traffic July 27 – August 14, 2022
  • Post-Rally 2022 – I-90 Westbound Construction
    • Begin work to replace the port of entry
    • Two-way traffic in the EB lanes
    • Perform culvert replacements under the WB lanes
    • Complete box culvert work under the WB lanes
    • Complete commercial vehicle screening system work in the WB lanes
    • Complete the WB On and Off-Ramp at Exit 37
      • WB On-Ramp traffic will be detoured to Exit 40
      • Exit 37 Ramp A Detour
    • Continue structure work at the new Exit 37 overpass bridge.
  • No work is anticipated along the roadway between October 29, 2022, and March 20, 2023
  • Pre-Rally 2023 – I-90 Eastbound Construction
    • Complete the port of entry construction
      • Includes the replacement of the on/off ramps to the port of entry
    • Two-way traffic in the WB lanes
    • Complete all commercial vehicle screening system work in the EB lanes
    • Complete culvert replacements under the EB lanes
    • Complete box culvert work under the EB lanes
    • Grading work for the realignment of Pleasant Valley Road
    • Reconstruct Exit 40 EB Off Ramp
      • Ramp will be closed with a detour to Exit 44.
      • Exit 40 Ramp D Detour
  • No work affecting traffic July 29 – August 13, 2023
  • Post-Rally 2023 – Pleasant Valley Road Construction
    • Demolition of existing Exit 37 bridge
    • Complete the realignment/reconstruction of Pleasant Valley Road
    • Demolition of median crossovers
  • Project completion Oct. 27, 2023

Project Phasing Maps:

  • Phase 3 (Pre-Rally 2023)
  • Phase 4 (Post-Rally 2022)

 

Contract Amount:

$35 Million


Project Contacts:

Contractor: 
Complete Concrete, Inc. dba
Complete Contracting Solutions
605-388-0111

SDDOT:
Jason Baker
605-209-3388

 STATEWIDE CONSTRUCTION PROJECTS PAGE

 

PCN - 021G

TransportationDoing Business
Certification & AccreditationContractorsEngineering/Design ServicesEnvironmentalLocal GovernmentsTraffic Incident Management
Projects & Studies
PlanningStudiesConstruction ProjectsSDDOT InnovationPublic Meetings
Programs & ServicesTravelersInside SDDOTDOT Fact BookBlogsHome test