U.S. Highway 12 - Aberdeen to Bath

Project Summary:
This project will include grading, concrete paving, lighting, pipework and a reinforced concrete box culvert. The project will enhance safety, with the addition of turn lanes and street lighting.
Traffic will be routed to the eastbound lanes.
Project Timeline:
April 24, 2023-November 2023.
Project Updates:
Aug. 23, 2023
August Completed Work: Traffic was switched to the westbound lanes and work on phase two, the eastbound lanes, has begun. The asphalt shoulders and approach pavement were placed for phase one. Topsoil placement and permanent seeding were also completed for phase one. The existing pavement on phase two has been removed and grading work has started.
Anticipated work in September: Grading work will continue. The second half of the box culvert near 394th Ave will be built. The mainline cross pipe will be installed and a gravel cushion will be placed on the mainline.
Project Photos:
Project Contract Amount:
$20.5 Million
Project Contacts:
Contractor:
Reede Construction Inc.
605-225-7085
SDDOT:
Bruce Shroeder
605-626-7885
STATEWIDE CONSTRUCTION PROJECTS PAGE
PCN: 05HT